STEM WATER DIST. & INFRA. CO. PVT. LTD., THANE













 

TENDER NOTICE NO. ______FOR 2023-2024


FOR

 

 




 






















 

Managing Director

STEM Water Distribution and Infrastructure Co. Pvt. Ltd.

Vardan Commercial Complex, 9th Floor, MIDC, Road No.16, Wagale Estate,

Thane (w) - 400 604.

 

 

 

 

 

STEM WATER DIST. & INFRA.CO.PVT. LTD., THANE

 

    Name of Work: - 

 

TENDER NOTICE NO.______FOR 2022-2023

Sr. No.

Description

Page No.

1

Detailed Tender Notice

 

2

Form B-1

 

3

Condition of Contract

 

4

General Conditions of Contract

 

5

Material Schedule – A

 

6

Detailed Itemwise Specification 

 

7

Schedule – B

 

8

Letter of Application

 

9

Affidavit

 

10

Undertaking

 

11

Affidavit (on Rs.500/- Stamp Paper)

 

12

Form of Bid

 

13

Performance of Bank Guarantee

 

14

Letter of Acceptance

 

15

Agreement Form

 

16

Notice to Proceed Work

 

17

Annexure (If Any)

 

18

Layout / General Arrangement Drawings

 

 

 

 

 

 

 

 

STEM WATER DIST. & INFRA.CO.PVT. LTD., THANE

DETAILED TENDER NOTICE NO.______FOR 2022-2023

               Managing Director on behalf of the STEM Water Distribution & Infrastructure Co. Pvt. Ltd., Thane invites tenders through E-Tendering Two envelop System for the following work on percentage rate B-1 tender basis from experienced contractors having valid registration of in appropriate class in (Elec./Mech) with MJP or in equivalent class (Elec./Mech) with any Govt./Semi Govt. Organization.

Sr. No.

Name of Work

Estimated cost 

(In Rs.)

Earnest Money Deposit

(In Rs.)

Cost of Tender

(In Rs.)

Period of Completion

1

/-

/-

/-

(Excluding GST)

(From Bidders own Bank Account)

(Including 18% GST)

Calendar months including monsoon

1) Security Deposit: -

    i.   Total % security deposit will be recovered.

    ii.  Initial Security Deposit will be% of estimated cost or contract value whichever is higher in the form of D.D/ Fixed Deposit Receipt/ Bank Guarantee from Nationalized /Scheduled Bank (Bank Guarantee valid up to the expiry of defect liability period) in favour of Managing Director, STEM water Distribution & Infrastructure Co. Pvt. Ltd., Thane

    iii.  Deductions through R.A. Bills.: Balance % security deposit of Estimated cost or contract value whichever is higher will be recovered at the rate of 5% of the bill amount through each R.A. Bill to the extent that total required security deposit is to be recovered.

        a)  Additional Performance Security Deposit: If the offer of the bidder is below of the estimated cost put to tender, the additional performance security deposit shall be furnished by the agency as below.                                                              

i)  If offer upto 10% below:            1% of estimated cost put to tender.                                                  
ii)  If offer more than 10 % Below:       

1% plus ____% below more than 10%

(Example If offer is below 14%: 1% + (14% - 10%) = 5%)

iii)  If offer more than 15% below:

6% Plus Double of the % more than 15%

below (Example If offer is below 19% then (19%- 15%) x 2= 8%+6%= 14%)

Additional Performance Security Deposit (APSD) shall be in the form of F.D.R. /D.D./BG of nationalized/ scheduled Bank only in the name of Managing Director, STEM. APSD should be submitted within 8 days to Managing Director from the date of intimation of letter from the STEM. No extension to 8 days period is admissible in any circumstances. APSD of successful bidder will be refunded after completion of work satisfactorily, with final bill.

If L1 fails to submit APSD within stipulated period, L-2, will be asked to negotiate the offer below to L-1 and submit the APSD within 8 days offer receipt of the letter from STEM.

 

  1. Stamp Duty –

 

(a)

Where the amount or value set forth in such contract does not exceed rupees ten lakh.

Five Hundred rupees stamp duty

 

(b)

 

Where it exceeds rupees ten lakhs

Five hundred rupees plus one hundred rupees for every Rs.1,00,000/- or part thereof, above rupees ten lakh subject to the maximum of rupees twenty- five lakh stamp duty

The contractor whose offer is accepted will be called for execution of the agreement and shall only be liable to pay the stamp duty applicable there on.

2)  Time of Completion: - () calendar months including monsoon. This will be 

                                                  Counted from the date of work order

3)  Date of submission of tender: - Upto

4)  Place of Submission: - The Contractor has to submit the Tender offline only at

                                            STEM Water Distribution and Infrastructure Co. Pvt. Ltd.

                                              Vardan Commercial Complex, 9th Floor, MIDC, Road                

                                              No.16, Wagale Estate, Thane (w) - 400 604.

5)  Cost of Blank Tender Form:-Rs./- (Including 18% GST)

                                         () (Non-refundable).

6)  Validity of the Offer: -60 (Sixty) days from the last date of receipt of the tender.

7)  Eligibility Criteria:

8)  Manner of Submission of Tender and its Accompaniments:

      Tender shall be submitted/ upload in two separate sealed Envelopes. The Tenderer shall submit the tender and documents in two sealed envelopes as below:

    a)  Envelope No.1:

          The First Envelope clearly marked as Envelope No.1 and name of work shall contain following documents.

        i)  Earnest Money Deposit as explained above. (e-EMD)

        ii)  Copy of Registration certificate in appropriate class.

        iii)  Copy of Experience Certificate and other certificates, documents as per P.Q.

        iv)  Copy of PAN and Goods& Services Tax Registration Number.

        v)  Copy of Affidavit on Rs. 100/- Stamp paper (Format attached)

        vi)  Copy of Minutes of Pre bid meeting. (if any).

        vii)  Copy of Constitution or Legal Status of Agency& Copy of Power of attorney (if any).

        viii)  Affidavit &undertaking as per format attached.

          All above documents shall be enclosed/submitted/ uploaded in the Envelope No.1, if any, of the above documents are not found in Envelope No.1, Envelope No. 2 will not be opened. Before rejection/ decision of non- opening envelop No. 2, one chance to fulfil the requirements/ documents with in specified period will be given as per decision of STEM (Tender Evaluation Committee) to bidders.

b)  Envelope No.2:

         The second Envelope Clearly marked as Envelope No.2 with name of work shall contain only main tender including unconditional covering letter. The Tenderer should quote his offer on printed ‘B’ forms (as per E-Tender procedure at appropriate place) of the tender as percentage of estimated rates in word and figure at the appropriated place of tender documents to be submitted only in Envelope No.2. He should not quote this offer anywhere directly or indirectly in Envelope No.1. The contractor shall quote for the work as per details given in the main tender. Offer shall be unconditional. All the documents mentioned in shall be submitted/upload offline at STEM Water Distribution and Infrastructure Co. Pvt. Ltd.

Vardan Commercial Complex, 9th Floor, MIDC, Road No.16, Wagale Estate, Thane (w) - 400 604.

The Bidders shall submit all the documents mentioned above in hard copy dully signed within 72 hrs. from last date, time of receipt in sealed envelope to the Accountant / Account Officer /Managing Director of STEM. Submission of hard copy is a requirement based on CVC guidelines & hence cannot be done away with. However, hard copies shall be opened only if there are problems in opening / downloading of tender offers. If the contractor inadvertently or otherwise does not submit hard copy, then it shall not constitute a bar to open his e- offer. His online tender shall be opened by the tender opening authority and shall be processed. If the contractor’s offer is lowest then it shall be accepted and his downloaded tender shall be treated as hard copy.

9) Opening of Tender:

The tenders will be opened on the date specified in the Tender Notice i.e., on___/___/2023 at 15.00 hrs. (if possible) in the presence of the intending bidders or their authorized representative to whom they may choose to remain present. Following procedure will be adopted for opening of the Tender.

Envelope No. 1

First of all Envelope No.1 of the Tender will be opened to verify its contents as per requirements by STEM’s Tender Evaluation Committee. If the various documents contained in this envelope do not meet the requirements of the STEM, a note will be recorded accordingly. Before rejection one chance to fulfil the requirements/ documents of envelop No.1 within specified period will be given as per decision of STEM and if not fulfilled requirements, the said Tenderer’s Envelope No.2 will not be considered for further action but the same will be rejected.

Envelope No.2

After opening of Envelope No.1 if contents of Envelope No.1 are found to be acceptable to the STEM Water Distribution & Infrastructure Co. Pvt. Ltd., Thane then only this Envelope No.2 shall be opened. The tendered rates in B-1 Form on the basis of percentage above/ below / at par of the estimated rates put to tender shall then be read out. After submission of Tender Bid (After Bid lock) and after opening of Technical Bid Envelope No.1 No request of Not to open Envelope No.2 is admissible. If bidders/contactors are complainting /at taking objections against each other OR complanting/objections on tender opening procedure then decision of M.D. STEM final and binding on bidders.

 10. GST TDS and Income Tax (At rate applicable as per entity), at the prevailing rate will be deducted from each R.A. / Final bill of the contractor till the agency has produced certificate from Income Tax Dept. to the effect that not to deduct Income Tax for this contract at source. 1% of actual value of work will be deducted from each R.A. Bill and Final Bill as a Labour cess under the provision of Building & other construction works welfare cess Act, 1996. No reimbursement on all this account will be admissible.


 11. The Bid shall be excluding of GST and inclusive of all existing taxes, duties, levies service charges, Cess, Custom duty, State / Central excise duty other applicable taxes as amended from time to time. No extra payment on this account shall be made to the contractor. Rise in any type of taxes, duties, levies, service charges, cess etc. or new taxes, duties, levies, service charges, cess etc. imposed by Government after quoting offer are also not admissible for reimbursement. Bidder Shall quote accordingly.


 12. Intending bidder / firm should have to produce valid PAN No. and GST Registration Number. It is responsibility to contractor to upload GST invoice on portal which is issued to STEM. It is bidder’s responsibility to comply anything / everything related to Section 171 (1) of GST Act, 2017 AND other provisions of GST Act time to time in force.


 13. All bidders are cautioned that tender containing any deviation from the contractual terms and conditions. Specifications or other requirements are liable to be rejected as non-responsive. Payment of excess quantities, claims and extra items, will be made only after approval of Board of Directors OR by appropriate authority of STEM. All materials/ equipment’s to be used for this work shall be fully tested at manufacturer’s works as per International Standards. All testing, inspection charges and other expenses shall be borne by the contractor only. Bidder shall quote accordingly.


 14. i) It is entirely bidder’s responsibility to upload / submit true / valid documents and STEM will not be responsible for the same. If it is found that bidder has uploaded / submitted any false / fraudulent documents, then his offer / tender will be rejected.  He will be black-listed.

ii)  Documents submitted along the R.A. Bill / Final Bill should be True / Valid. If the bidder has submitted / attached / enclosed / uploaded any false / fraudulent documents / papers then concerned bidder will be blacklisted and criminal offence as per Indian Penal Code will be registered against such bidder by STEM.


 15. Earnest Money Deposit of the unsuccessful bidder except of L1 & L2 will be returned after opening of Envelope No. 2 (Price Bid) and after issuance of work order Earnest Money Deposit of L2 will be returned.


 16. In case of dispute or difference arising between the STEM Company and the Contractor, relating to any matter arising out of or connected with this agreement, the dispute or differences shall be referred to Chairman, Board of Directors STEM as a sole Arbitrator by agreement between the parties. The venue of the arbitration shall be Thane, the language shall be English. The cost and expensed of such arbitration shall be borne equally by the parties hereto. The award of sole Arbitrator shall be binding upon the parties to the disputes.


 17. The contractor’s those who are black listed or cancelled/proposed to cancel their registration from STEM/ Government/Semi Government/ Local Authorities/ Municipal Corporation / PUC etc. they are not eligible to quote the bid/offer. If fake documents are submitted by bidders (i.e., BG / FDR / Reg. Certificate / experience certificate or any other documents) during bid submission the bidder's EMD will be forfeited & liable for black listing action.


 18. A consistent history of litigations/awards against the Bidder will result in rejection of the bid. Suppression of any information or material in this regard would be construed as a fundamental breach and STEM reserves its right to take appropriate action including cancellation of the bid, forfeiting of bid security etc., as may be deemed fit by STEM at any time without requiring to give any notice to the applicant in this regard.


 19. All other rules regarding Insurances, Workman’s compensation, Labour, ESIC, EPF, Medical Exp. facility etc. shall be binding on the contractor. The contractor shall be responsible to pay compensation to his staff, labours according to labour compensation rules, labour laws, on account of any accident and loss of limb, or life, property due to accident etc. Bidder shall quote accordingly. STEM will not be responsible if any liability arise in future for Non-Compliance of any laws and related amendments by the contractor.

The successful bidder shall submit valid registration certificate under E.S.I.C., Act 1948, if the tenderer has more than 10 employees /persons on his establishment (in case of production by use of energy) and 20 employees/persons on his establishment (in case of production without use of energy) to STEM as and when demanded. In case of less employees/persons mentioned above then the successful bidder has to submit an undertaking to that effect on Rs. 500 stamp papers.

The successful bidder shall submit valid registration certificate under E.P.F. &M.P., Act 1952, if tenderer has more than 20 employees/persons on his establishment, to STEM as and when demanded. In case if the successful bidder has less employees/persons mentioned above then the successful bidder has to submit an undertaking to that effect on Rs. 500 stamp papers.

 20. Contractor shall take out all necessary Insurance Policy / Policies so as to provide adequate insurance cover for execution of the awarded contract work and for total contract work and for total contract value and for complete contract period compulsorily from the Directorate of Insurance, Maharashtra State, Mumbai Only. Under any circumferences, insurance from any other insurance company will not be accepted. Insurance policies also for extended period and up to DLP to be drawn and borne by contractor. Bidder/ Contractor shall quote accordingly.

 21. The bidder shall bear all costs associated with the preparation and submission of his Bid, and the STEM will in no case be responsible and liable for those costs, including Cost of Tender form.

 22. The Bidder, at the Bidder's own responsibility and risk is encouraged to visit and examine the Site of Works and its surroundings and obtain all information that may be necessary for preparing the Bid and entering into a contract of the Works. The costs of visiting the Site shall be at the Bidder's own expense. The bidder is expected to examine carefully all instructions, conditions of contract, contract data, forms, terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid Document. (Including minutes of Pre bid if any) Failure to comply with the requirements of Bid Documents and offer shall be at the bidder's own risk.

 23. Bids shall remain valid for a period not less than 60 daysafter the deadline date for bid submission specified. A bid valid for a shorter period shall be rejected by the STEM as non-responsive. In exceptional circumstances, prior to expiry of the original validity, STEM may request that the bidders may extend the period of validity for additional period. The request and the bidders' responses shall be made in writing. A bidder may refuse the request without forfeiting his bid security.

 24. STEM will reject a proposal for award if it determines that the Bidder recommended for award has engaged in corrupt or fraudulent practices in competing for the contract in question and will declare the firm ineligible, either indefinitely or for a stated period of time, to be awarded a contract with any other agencies, if it at any time determines that the firm has engaged in corrupt or fraudulent practices in competing for the contract, or in execution.

 25.  Conditional Tender will be rejected. Right to reject any or all tenders without assigning any reason thereof is reserved by the Competent Authority of STEM whose decision will be final and binding on tenderers.

 26.  In case of any clarification required with respect to contradictory provisions in B-1 form and other papers of tender, provision stated in this tender notice from Sr. No.1 to 25 above shall stands supersedes to effect contradictory provisions and shall prevail.

 27. GOODS AND SERVICES TAX (G.S.T.)

   1 a) Bidder shall quote his rate excluding GST.

       c) GST shall be paid on the amount of bill of the work done as per prevailing guideline rate of GST during the period of work done as applicable.

        d) The rate quoted by the contractor shall be deemed to be inclusive of theLabour Welfare Cess and other taxes (other than GST) that the contractor will have to pay for the performance of contract. The employer will perform such duties in regard to the deduction of such taxes at source asperapplicablelaw.

2 a)The contractor should get him self acquainted with GST act 2017.

    b) Amount of GST 2% i.e., CGST and SGST each 1% will be deducted at source(TDS).

 

28. RIGHT RESERVED

a) Right to reject any or all tenders without assigning any reason there of is reserved by the competent authority, whose decision will be final and legally binding on all the tenderer.


















Managing Director

STEM Water Dist. & Infra. Co. Pvt. Ltd.,

Thane.

 



 

FORM B-1

STEM WATER DISTRIBUTION & INFRASTRUCTURE CO. PVT. LTD.,THANE

PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS

DEPARTMENT : STEM Water Distribution & Infrastructure Co. Pvt. Ltd. 

DIVISION: Operation/ Project/ FDC

GENERAL RULES & DIRECTIONS FOR THE GUIDANCE OF CONTRACTORS



1

All works, proposed to be executed by Contract, shall be notified in a Form of invitation to tender, pasted on a Notice Board hung up in the office of the Managing Director/ Published in News Paper's. This form will state the works to be carried out as well as the date of submitting and opening tenders, and the time allowed for carrying out the work, also the amount of earnest money to be deposited with the tender, and the amount of the security deposit to be deposited by the successful Tenderer and the percentage, if any, to be deducted from bills. Copies of any other documents required in connection with the work shall be signed by the Managing Director for the purpose of identification and shall also be open for Inspection by Contractors at the office of the Managing Director during office hours/ Available On-line. Where the works are proposed to be executed according to the specifications recommended to a Contractor and approved by a competent authority on behalf of the STEM Water Distribution & Infrastructure Co. Pvt. Ltd., Thane, such specifications, with designs and drawings shall form a part of the accepted tender.

2

In the event of the tender, being submitted by a firm, it must be signed by Partner thereof, and in the event of the absence of any Partner, it shall be signed on his behalf by a person holding a power of attorney authorizing him to do so.

2. A (i)

The Contractor shall pay along with the tender the sum of Rs. 2,100/- (Rupees Two Thousand One Hundred only) as and by way of Earnest Money. The said amount of earnest money shall not carry any interest whatsoever. The contractors should have to submit EMD as per E- Tendering procedure.

(ii)

In the event of his tender being accepted to the provisions of Sub-Clause (iii) below, the said amount of Earnest Money Deposit shall be appropriated towards the amount of security deposit payable by him under conditions of General Conditions of Contract if the contractor request so in writing.

(iii)

If after submitting the tender, the Contractor withdraws his offer or modifies the same, or if after the acceptance of his tender, the Contractor neglects to furnish the balance amount of Security Deposit without prejudice to any other rights and powers of the STEM, Contractor shall be entitled to forfeit the full amount to the Earnest Money deposited by him.

(iv)

In the event of his tender not being accepted, the amount of Earnest Money deposited by the Contractor shall unless it is prior thereto forfeited under the provisions of Sub-Clause (iii) above, be refunded to him on his passing receipt therefore.

3

Receipts for payments made on account of any work, when executed by a firm should also be signed by all the partners except where the contractors are 

described in their tender as firm, in which case the receipt shall be signed in the name of the firm by one of the partners, or by some other person having authority to give effectual receipts of the firm.

4

Any person who submits a tender shall fill up usual printed form stating to what percentage above or below the rates specified in Schedule-B (Memorandum showing Item of work to be carried out) he is willing to undertake the work. Only one rate or such percentage on all estimated rates/scheduled rates shall be named, tenders which propose any alterations in the works specified in the said form of invitation to tender or in the time allowed for carrying out the work or which contain separate percentage over estimated rates / schedule rates for different sub-work or item, or which contain any other conditions, of any sort which are not filled with the percentage as the space provided for the purpose and not signed at proper place in the printed B-1 Tender Form will be liable for rejection. No printed form of tender, shall include a tender for more than one work. But, if the contractors who wish to tender two or more works, they shall submit a tender for each work separately. Tenders shall have the name and number of the work to which they refer, written outside the Envelopes/ As per e- tender procedure.

5

The Managing Director or the competent authority or General Manager or his duly authorized Assistant shall open tenders in the presence of contractors who have submitted tenders or their representatives who may be present at the time, and he will enter the amounts of the several tenders in a comparative statement in a suitable, form. In the event of a tender being accepted, the contractor shall for the purpose of identification, sign copies of the specification and other documents mentioned in Rule-1. In the event of tender being rejected, the Managing Director shall arrange to refund the amount of the earnest money deposited to the tenderer, on his giving a receipt for the return of the money.

6

The officer competent to dispose of the tenders shall have the rights of rejecting all or any of the tenders. (MD- STEM/ BoD- STEM).

7

No receipt for any payment alleged to have been made by a contractor in regard to any matter relating to this tender or the contract shall be valid and binding on STEM Water Distribution & Infrastructure Co. Pvt. Ltd., Thane unless it is signed by the Managing Director.

8

The memorandum of work to be tendered for the schedule of materials to be supplied by the STEM Water Distribution & Infrastructure Co. Pvt. Ltd., Thane (hereinbefore and after called as "STEM" for brevity) and their rates shall be filled in and completed by the office of the Managing Director before the tender form is issued. If a form issued to an intending Tenderer has not been so filled in and completed he shall request the said office to have this done before he completes and delivers his tender.

9

All work shall be measured net by standard measure and according to the rules and customs of the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane without reference to any local custom.

10

Under no circumstances shall any contractor be entitled to claim enhanced rates for items in this contract.

11

Every registered contractor should produce along with his tender certificate of registration as approved contractor in the appropriate class and renewal of such registration with date of expiry.(Now as per Detail Tender Notice and as per PWD G. M GR’s Circulars in force.)

12

The measurements of work shall be taken according to the usual methods in use in the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane and no proposals to adopt alternative methods will be accepted. The Managing Director’s decision as to what is the usual method in use in the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane will be final.

13

The tendering Contractor shall furnish a declaration along with the tender showing all works for which he has already entered into contract, and the value of the work that remains to be executed in each case on the date of submitting the tender such certificate shall be in the proforma attached in the tender document.

14

Every Tenderer shall furnish along with the tender information regarding the Income-tax Circle or Ward of the district in which he is assessed to Income-tax, the reference to the number of the assessment and the assessment year and a valid Income-tax clearance certificate.

15

In view of the difficult position regarding the availability of foreign exchange, no foreign exchange would be released by the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane for the purchase of plant and machinery or any other purpose for the execution of the work contracted for.

16

Every contractor / bidder should furnish along with tender a statement showing previous experience and technical staff employed by him.

17

Successful Tenderer will have to produce to the satisfaction of the accepting authority a valid and current license issued in his favour under the provision of Contract Labour (Regulation and Abolition Act, 1973) before starting work failing which acceptance of the tender will be liable for withdrawal and Earnest Money / Security Deposit will be forfeited to Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane.

18

The contractor shall comply with the provisions of the Apprentices Act 1961 and the rules and orders issued there under from time to time. If he fails to do so, his failure will be a breach of the contract and the Managing Director, STEM Water Dist. & Infra. Co. Pvt. Ltd., Thane may, in his discretion cancel the contract. The Contractor shall also be liable, for any pecuniary liability arising on account of any violation by him of the provisions of the Act.

in figure as well as in words.

I/We hereby tender for the execution for the Stem Water Distribution Infrastructure Co. Pvt. Ltd., Thane (hereinbefore and hereinafter referred to as STEM of the work specified in the underwritten memorandum within the time specified in such memorandum at__________________________________________________________________________________________________________________________________________percent below/above (in figure and word) to the estimated rates entered in Schedule B (memorandum showing items of work to be carried out) and in accordance in all respects with the specifications, designs, drawings and instructions in writing referred to in Rule 1 hereof and in clause 12 and the annexed conditions of contract and agree that what materials for the work are provided by the Stem Water Distribution Infrastructure Co. Pvt. Ltd., Thane such materials and the rates to be paid for them shall be as provided in Schedule here. As per E-Tender Procedure)





 



 



MEMORANDUM

1.(A)

Name of Work:-



 

a) If several sub works are included, same should be detailed in a separate list.


 

B)

Estimated cost (Excluding GST):/-

C)

Earnest money: Rs. /-

c) The amount of earnest money to be deposited shall be in accordance with the provision of paras 206 and 207 ofthe MPW Manual/ As per PWD, GR dtd. 27/09/2018.

D)

Security deposit: Total 2% of estimated cost

d) This deposit shall be in accordance with the paras 213 and 214 of the MPW Manual/ As per PWD, GR Dtd. 27/09/2019. C/R.CAT/2017/PK-08/E2.

 

2% Initial Security Deposit shall be in form of FDR / DD from any Nationalized / Scheduled Bank- 

 

E)

-

e)                              -

F)

Additional Performance Security Deposit/ D.D./ FDR/ B.G. of any Nationalised/ As per PWD GR dtd. 29.09.2018.Circular Dt.26.11.2018 (At/2017/DK-8/EM-2)

f) If additional security deposit  

 
 

i) If offer upto 10% below

1% of estimated cost put to tender.

 

ii) If offer more than 10%

1% plus ____% below more than 10%    (e.g. If offer is below 14% : 1% + (14% -10%) = 5%)

 

iii) If offer more than 15% below

6% Plus Double of the % more than 15% below (e.g. If offer is below 19% then    (19% - 15%) x 2= 8% + 6%= 14%)

G)

Time allowed for the work from date of written order to completion 1 (One) calendar months including monsoon.  

g) Give Schedule where necessary showing dates by which the various items are to be completed.

2

I/We agree that the offer shall remain open for a minimum period of 60 days from the last date fixed for bid submission specified and thereafter until it is withdrawn by me/us by notice in writing duly addressed to the authority opening the tenders and sent by registered post A. D. or otherwise delivered at the office of the such authority. e-EMD/ Term Deposit Receipt No. / Demand Draft No. ________ dated _______________). And date in respect of sum of Rs.______________inwords (Rs._______________________________________________________) is enclosed. The amount of earnest money shall be liable to be forfeited to the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane should I/We fail to (i) abide by the stipulation to keep the offer open for the period mentioned above or (ii) sign and complete the contract documents as required by the Managing Directorand furnish the security deposit as specified in item (d) of the memorandum contained in paragraph (1) above within the time limit laid down in clause (1) of the annexed General Conditions of Contract, the amount of earnest money may be adjusted towards the security deposit or refunded to me/us if so desired by me/us in writing unless the same or any part thereof has been forfeited as aforesaid. 

3

Rules and Conditions of the contract are subject to amendment till the timeof acceptance of tender. The Successful contractor will have to enter into agreement in form specified by STEM Water Distri. & Infra. Co. Pvt. Ltd., Thane on a stamp of required amount as per rules in force. The stamp charges shall be borne by the contractor.

4

Should this tender be accepted I/We hereby agree to abide by and fulfil all the terms and provisions of the conditions of contact annexed hereto so far as  applicable  and  in  default  hereof  to  forfeit  and  pay to  Stem  Water Distribution & Infrastructure Co. Pvt. Ltd.,  Thane the sums  of money mentioned in the said conditions.

*Amount to be specified in words & figures

Term Deposit Receipt No. _______________ dated ___________ from the Bank.*


 

* Name of the bank to be specified

At___________________________________________________ in respect of the sum of *Rs._____________/- (Rupees________________________________________________________________________________________________ only) 

Strike out (a) if no case security deposit is to be taken

is herewith forwarded representing the earnest money (a) the full value of which is to be absolutely forfeited to Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane should I/We not deposit the full amount of security deposit specified in the above memorandum in accordance with (d) of clause (1) of the tender for works shall be refunded.

(**) Signature of Contractor before submission of tender.

Contractor                                         (**)

Address


 

Dated the

day of

   

200

   

# Signature of witness 

(Witness)#

(Witness)#

Address

(Occupation)

 

PAN No.

 

The above tender is hereby accepted by me for and on behalf of the Stem Water Distribution & Infrastructure Co. Pvt. Ltd., Thane.

 

(*) Signature of the officer by
whom
accepted.

 

Accepted for Rs. ____________ in words (Rupees_____________________________________________________________________) ______% above/ below/ at par to the estimated cost put to tender Rs._______________. (Rupees.______________________________________________________________________)


 

Managing Director

STEM Water Distri. & Infra. Co. Pvt. Ltd., Thane.

                   

 

 

 

 

CONDITIONS OF CONTRACT

Clause 1:- The person/persons whose tender may be accepted (hereinafter called the Contractor, which expression shall unless excluded by or repugnant to the context include his heirs, executors, administrators, and assigns ) shall (A) within 10 days (which may be extended by Managing Director, STEM concerned upto 15 days if Managing Director, STEM thinks fit to do so) of the receipt by him of the notification of the acceptance of his tender deposit with the Managing Director, STEM in cash or D.D./ FDR or Government securities endorsed to the Managing Director, STEM(if deposited for more than 12 months) of the sum sufficient which will made up the full security deposit specified in the tender or (B) (Permit STEM at the time of making any payment to him for work done under the contract to deduct such as will amount to two percent of all moneys so payable such deductions to be held by STEM by way of security deposit.) Provided always that in the event of the Contractor depositing a lump sum by way of security deposit as contemplated at above, then and in such case, if the sum so deposited shall not amount to two percent of the total estimated cost of the work, it shall be lawful for STEM at the time of making any payment to the Contractor for work done under the contract to make up the full amount of two percent by deducting sufficient sum from every such payment as last aforesaid until the full amount of the security deposit is made up. All compensation or other sums of money payable by the Contractor to STEM under the terms of his contract may be deducted from or paid by the sale of sufficient part of his security deposit or from the interest arising there form, or from any sums which may be due or may become due by STEM to the Contractor under any other contract or transaction of any nature on any account whatsoever and in the event of his security deposit being reduced by reason of any such deduction or sale as aforesaid, the Contractor shall within ten days thereafter, make good in cash or Government securities endorsed as aforesaid any sum or sums which may have been deducted from, or raised by sale of his security deposit or any part thereof. The security deposit referred to, when paid in cash may, at the cost of the depositor, be converted into interest bearing securities provided that the depositor has expressly desired this in writing. The security deposit will not be accepted in forms of insurance company bonds. If the amount of the security deposit be paid in a lump sum within the period specified at (A) above is not paid the tender/contract already accepted shall be considered as cancelled and legal steps taken against the Contractor for recovery of the amounts. The amount of the security deposit lodged by a Contractor shall be refunded after satisfactory completion of Defect Liability Period. In the event of the Contractor failing or neglecting to complete rectification work within the period upto which the Contractor has agreed to maintain the work in good order, then subject to provision of Clauses 17 and 20 hereof the amount of Security Deposit retained by STEM shall be adjusted towards the excess cost incurred by STEM on rectification work. (for refund of S.D provisions of PWD GR No.(AT/2017/PK-8 Dt.29.01.2019 are applicable)

Security Deposit

Clause 2:-“The time allowed for carrying out the work as entered in the tender shall be strictly observed by the Contractor and shall be reckoned from the date on which the order to commence the work is given to the Contractor. The work shall through the stipulated period of the contract be proceeded with, with all due diligence (time being deemed to be the essence of the contract on the part of the Contractor) and Contractor shall pay as compensation an amount equal to one percent or such smaller amount as the Managing Director, STEM (whose decision in writing shall be final) may decide, of the amount of the estimated cost of the whole work as shown by the tender for every day that the work remains uncommenced or unfinished after the proposed dates . And further to ensure good progress during execution of the work, the contractor shall be bound in all cases in which the time allowed for any work exceeds one month to complete. 25 % of the work in ** 1/4 of the time 50 % of the work in 1/2 of the time 100 % of the work in 1 (One)months Full work to be completed in1 (One)months including monsoon. In the event of the contractor failing to comply with this condition he shall be liable to pay as compensation an amount equal to one percent or such smaller amount as Managing Director, STEM (whose decision in writing shall be final) may decide of the said estimated cost of the whole work for every day that due quantity, of work remains incomplete. Provided always that the total amount of compensation to be paid under the provisions of this clause shall not exceed 10 per cent of the estimated cost of the work as shown in the tender. Managing Director, STEM shall be the final authority in this respect, irrespective of the fact that the tender is accepted by Managing Director, STEM.

Compensation for delay

Clause 3:- In any case in which under any clause of this contract the contractor shall have rendered himself liable to pay compensation amounting to the whole of this security deposit (whether paid in one sum or deducted by installments) or in the case of abandonment of the work owing to serious illness or death of the contractor or any other cause, the Managing Director, of the STEM Water Dist. & Infra. Co. Pvt. Ltd., shall have power to adopt any of the following courses, as he may deem best suited to the interest of STEM :- (a) To rescind the contract (for which rescission notice in writing to the contractor under the hand of Managing Director, STEM shall be conclusive evidence) and in that case the security deposit of the contractor shall stand forfeited and be absolutely at the disposal of STEM. (b) To carry out the work or any part of the work departmentally debiting the contractor with the cost of the work, expenditure incurred on tools and plant, and charges on additional supervisory staff including the cost of work-charged establishment employed for getting unexecuted part of the work completed and crediting him with the value of the work done departmentally in all respects in the same manner and at the same rates as if it had been carried out by the contractor under the terms of his contract. The certificate of the Managing Director, STEM as to the costs and other allied expenses so incurred and as to the value of the work so done departmentally shall be final and conclusive against the contractor. (c) To order that the work of the contractor be measured upto and take such part thereof as shall be unexecuted out of his hands, and to give it to another contractor to complete, in which case all expenses incurred on advertisement for fixing a new contracting agency, additional supervisory staff including the cost of work charged establishment and the cost of the executed by the new contract agency will be debited to the contractor and at the value of the work done or executed through the new contractor shall be credited to the contractor in all respects and in the same manner and at the same rates as if it had been carried out by the contractor under the term of his contract. The certificate of the Managing Director, STEM as to all the cost of the work and other expenses incurred as aforesaid for or in getting Action when whole of security deposit is forfeited. the unexecuted work done by the new contractor and as to the value of the work so done shall be final and conclusive against the contractor. In case the contract shall be rescinded under clause (a) above the Contractor shall not be entitled to recover or be paid, any sum for any work there for actually performed by him under this contract unless and until the Managing Director, STEM shall have certified in writing the performance of such work and the amount payable to him in respect thereof and he shall only be entitled to be paid the amount so certified. In the event of either of the courses referred to in clause (b) or (c) being adopted and the cost of work executed departmentally or through a new contractor and other allied expenses exceeding the value of such work credited to the Contractors, the amount of excess shall be deducted from any money due to the Contractor, by STEM under the contract or otherwise howsoever or from his security deposit or the sale proceeds thereof provided, however that the Contractor shall have no claim against STEM even if the certified value of the work done departmentally or through a new contractor exceeds the certified cost of such work and allied expenses, provided always that whichever of the three courses mentioned in clauses (a) , (b) or (c) is adopted by the Managing Director, STEM, the Contractor shall have no claim to compensation for any loss sustained by him by reason of his having purchased, or procured any materials, or entered into any engagements or made any advances on account of, or with a view to the execution of the work or the performance of the contract. The extra cost involved in the completion of the balance work carried out through the others contract under clause - 3(C) shall be recoverable from the contractor over and above the compensation levied under Clause 2 and the Security Deposit shall be apportioned against the total recoveries for this purpose also.

Action when whole of security deposit is forfeited.

Clause 4:- If the progress of any particular portion of the work is unsatisfactory, the General Manager, STEM shall not withstanding that the general progress of the work is in accordance with the conditions mentioned in clause 2, be entitled to take action under clause 3(b) after giving the Contractor 10 days notice in writing. The Contractor will have no claim for compensation, for any loss sustained by him owing to such action.

Action when the progress of any particular portion of the work is unsatisfactory.

Clause 5:- In any case in which any of the powers conferred upon the Managing Director, STEM by clause 3 and 4 hereof shall have become exercisable and the same shall not have been exercised, the non exercise thereof shall not constitute a waiving of any of the conditions hereof and such powers shall notwithstanding be exercisable in the event of any future case of default by the contractor for which under any clause hereof he is declared liable to pay compensation amounting to the whole of his security deposit and the liability of the contractor for past and future compensation shall remain unaffected. In the event of the Managing Director, STEM taking action under sub - clause (a) or (c) of clause 3,he may, if he so desires, take possession of all or any tools, plant, materials and stores, in or upon the works or the site thereof or belonging to the contractor, or procured by him and intended to be used for the execution of the work or any part thereof, paying or allowing for the same in account at the contract rates, or in the case of contract rates not being applicable at current market rates, to be certified by the Managing Director, STEM whose certificate thereof shall be final. In the alternative, the Managing Director, STEM may, after giving notice in writing to the contractor or his clerk of the work, foreman or other authorized agent require him to remove such tools and plants, materials, or stores from the premises within a time to be specified in such notice, and in the event of the contractor failing to comply with any such requisition, the Managing Director, STEM may remove them at the contractor’s expenses or sell them by auction or private sale on account of the contractor and at his risk in all respects, and the certificate of the Managing Director, STEM as to the expenses of any such removal and the amount of the proceeds and expense of such sale shall be final and conclusive against the Contractor.

Contractor remains liable to pay compensation if action not taken under Clause 3 &4

Clause 6:- If the Contractor shall desire an extension of the time for completion of work on the ground of his having been unavoidably hindered in its execution or on any other grounds, he shall apply in writing to the General Manager, STEM before the expiry of the period stipulated in the tender or before the expiration of 30 days from the date on which he was hindered as aforesaid or on which the cause for asking for extension occurred, whichever is earlier and the General Manager, STEM, may if in his opinion, there were reasonable grounds for granting an extension, grant such extension as he thinks necessary or proper. The decision of the Managing Director, STEM in this matter shall be final.

Extension of time.

Clause 7:- On the completion of the work the Contractor shall be furnished with a certificate by the Managing Director, STEM of such completion, but no such certificate shall be given nor shall the work be considered to be completed until the Contractor shall have remove from the premises on which the work shall have been executed, all scaffolding, surplus materials and rubbish and shall have cleaned off the dirt from all woodwork, doors, windows, walls, floor or other parts of any building in or upon which the work has been executed, or of which he may have had possession for the purpose of executing the wok nor until the work shall have been measured by the Engineer-in-charge or where the measurements have been taken by his subordinates until they have received approval of the Engineer-in-charge, the said measurements being binding and conclusive against the contractor. If the Contractor shall fail to comply with the requirements of this clause as to the removal of scaffolding, surplus materials and rubbish and the cleaning of dirt on or before the date fixed for the completion of the work the Engineer-in-charge may at the expense of the Contractor, remove such scaffolding, surplus materials and rubbish, and dispose off the same as he thinks fit and clean off such dirt as aforesaid and the Contractor shall forthwith pay the amount of all expenses so incurred, but shall have no claim in respect of any such scaffolding or surplus materials as aforesaid except for any sum actually realised by the sale thereof.

Final Certificate

Clause 8:- No payment shall be made for any work, estimated to cost less than Rupees One Thousand till after the whole of work shall have been completed and a certificate of completion given. But in the case of works estimated to cost more than Rupees One Thousand, the Contractor shall on submitting a monthly bill therefore, be entitled to receive payment proportionate to the part of the work then approved and passed by the Engineer - in- charge, whose certificate if such approval and passing of the sum so payable shall be final and conclusive against the Contractor. All such intermediate payments shall be regarded as payments by way of advance against the final payments only and not as payments for work actually done and completed, and shall not preclude the Engineer-in- charge from requiring any bad, unsound, imperfect or unskillful work to be removed or taken away and reconstructed or re-erected nor shall any such payment be considered as an admission of the due performance of the Contract or any part thereof in any respect or the occurring of any claim, nor shall it conclude, determine or affect in any other way the powers of the Engineer- in-charge as to the final settlement and adjustment of the accounts or otherwise, or in any other way vary or affect the Contract. The final bill shall be submitted by the Contractor within one month of the date fixed for the completion of the work. otherwise the Engineer-in-charge's certificate of the measurements and of the total amount payable for the work shall be final and binding on all parties.

Payment on intermediate certificate to be regarded as advances.

Clause 9:- The rates for several items of works estimated to cost more than Rs.1000/- agreed to within shall be valid only when the item concerned is accepted as having been completed fully in accordance with the sanctioned specifications. In cases where the items of work are not accepted as so completed, the Engineer-in-charge may make payment on account of such items at such reduced rates as he may consider reasonable in the preparation of final or on-account bills.

Payment at reduced rates on account of items of work not accepted as completed to be at the desecration of the Engineer in charge.

Clause 10:-A bill shall be submitted by the Contractor in each month on or before date fixed by the Engineer-in-charge for all works executed in the previous month, and the Engineer-in-charge shall take or cause to be taken the requisites measurement for the purpose of having the same verified and the claim, so far as it is admissible, shall be adjusted, if possible, within ten days from the presentation of the bill. If the Contractor does not submit the bill within the time fixed as aforesaid, the Engineer-in- charge may depute a subordinate to measure up the said work in the presence of the Contractor or his duly authorized agent whose countersignature to the measurement list shall be sufficient warrant, and the Engineer-in-charge may prepare a bill from such list which shall be binding on the Contractor in all respect.

Bill to be submitted monthly.

Clause 11:- The Contractor shall submit all bills in the electronic forms to be had on application at the office of the Engineer-in-charge. The charges to be made in the bills shall always be entered at the rates specified in the tender or in the case of any extra work ordered in pursuance of these conditions and not mentioned or provided for in the tender, at the rates hereinafter provided for such work.

Bills to be in electronic form.

Clause 12:- If the specification or estimate of the work provides for the use of any special description of material to be supplied from the stores of the STEM store or if it is required that the contractor shall use certain stores to be provided by the Engineer-in-charge (such material and stores and the prices to be charged therefore as hereinafter mentioned being so far as practicable for the convenience of the contractor but not so as in any way to control the meaning or effect of this contract specified in the schedule or memorandum hereto annexed) the contractor shall be supplied with such materials and stores as may be required from time to time to be used by him for the purpose of the contract only, and the value of the full quantity of the materials and stores so supplied shall be set off or deducted from any sums then due or thereafter to become due to the contractor under the contract, or otherwise, or from the security deposit, or the proceeds of the sale thereof, if the security deposit is held in STEM securities, the same or a sufficient portion thereof shall in that case be sold for the purpose. All materials supplied to the contractor shall remain the absolute property of STEM and shall on no account be removed from the site of the work, and shall at all times be open to inspection by the Engineer-in- charge. Any such materials unused and in perfectly good condition at the time of completion or determination of the contract shall be returned to the STEM store, if the Engineer-in-charge so requires by a notice in writing given under his hand, but the contractor shall not be entitled to return any such materials except with consent of the Engineer- in-charge and he shall have no claim for compensation on account of any such material supplied to him as aforesaid but remaining unused by him or for any wastage or damage to any such materials. The Contractor shall however, return all unused material at the time of completion, which was issued to him free of cost by the Engineer-in-charge and which has remained surplus with the contractor after accounting for the actual utilisation of such material from the total quantity that was issued by the Engineer-in-charge. Cost of any material issued free of cost by by the Engineer and which has remained surplus with the contractor but has not returned back by him to the Engineer, shall be recovered by the Engineer from the contractor at the issue rate of STEM Water Distri. & Infra. Co. Pvt. Ltd., Thane or market rate whichever is more.

Stores supplied by
STEM Water
Dist. & Infra.
Co. Pvt. Ltd.

Clause 12 ( A ):- All stores of controlled materials such as cement, steel etc., to be supplied by STEM to the contractor should be kept by the contractor under lock and key and will be accessible for inspection by the General Manager, STEM or his agent at all the times.

Storage of controlled material

Clause 13:- The contractor, shall execute the whole and every part of the work in the most substantial and workman like manner, and both as regards materials and every other respect in strict accordance with specifications. The contractors shall also conform exactly, fully and faithfully to the designs, drawings and instructions in writing relating to the work signed by the Engineer-in-charge and lodged in his office and to which the contractor shall be entitled to have access for the purpose of inspection at such office, or on the site of the work during office hours. The contractor will be entitled to receive three sets of contract drawings and working drawings as well as one certified copy of the accepted tender along with the work order free of cost. Further copies of the contract drawings and working drawings if required by him, shall be supplied at the rate of Rs.300/- per set of contract drawings and Rs.150/- per working drawing except where otherwise specified.

Works to be executed in accordance with specifications drawings, orders, etc.

Clause 14:- The Managing Director shall have power to make any alterations in or additions to the original specifications, drawings, designs, and instructions that may appear to him to be necessary or advisable during the progress of the work, and the Contractor shall be bound to carry out the work in accordance with any instructions in this connection which may be given to him in writing signed by the Managing Director and such alteration shall not invalidate the contract, and any additional work which the Contractor may be directed to do in the manner above specified as part of the work shall be carried out by the Contractor on the same conditions in all respects on which he agreed to do the main work, and at the same rates as are specified in the tender for the main work. And if the additional and altered work includes any class of work for which no rates is specified in this contract, then such class of work shall be carried out at the rates entered in the Schedule of Rates of the Division prevailing at the time when the extra items crop up or at the rates mutually agreed upon between the STEM and the contractor whichever are lower. If the additional or altered work for which no rate is entered in the Schedule of Rates, is ordered to be carried out before the rates are agreed upon then the Contractor shall within seven days of the date of receipt by him of the order to carry out the work inform the Managing Director through General Manager of the rate which it is his intention to charge for such class of work, and if the Managing Director does not agree to this rate, he shall by notice in writing be at liberty to cancel his order to carry out such class of work, and arrange to carry it out in such manner as he may consider advisable provided always that the Contractor shall commence work or incur any expenditure in regard thereto before the rates shall have been determined as lastly here in before mentioned, then in such case he shall only be entitled to be paid in respect of the work carried out or expenditure incurred by him prior to the date of the determination of the rates as aforesaid according to such rate or rates as shall be fixed by the Managing Director. In the event of a dispute, the decision of the BoD, STEM will be final. Where, however, the work is to be executed according to the designs, drawings and specifications recommended by the contractor and accepted by the competent authority the alterations above referred to shall be within the scope of such designs, drawings and specifications appended to the tender. The time limit for the completion of the work shall be extended in the proportion that the increase in its cost occasioned by alterations or additions bears to the cost of the original contract work, and the certificate of the Engineer-in-charge as to such proportion shall be conclusive.

Rates for works not entered in estimate, or schedule of rates of the contract.

Clause 15:- Clause 15: (1) If at any time after the execution of the contract documents, the Managing Director shall for any reason what-so-ever (other than default on the part of the Contractor for which the STEM is entitled to rescind the contract) desires that the whole or any part of the work specified in the tender should be suspended for any period or that the whole or part of the work should not be carried out at all, he shall give to the Contractor a notice in writing of such desire and upon the receipt of such notice the Contractor shall forthwith suspend or stop the work wholly or in part as required, after having due regard to the appropriate stage at which the work should be stopped or suspended so as not to cause any damage or injury to the work already done or endanger the safety thereof provided that the decision of the Managing Director as to the stage at which the work or any part of it could be or could have been safely stopped or suspended shall be final and conclusive against the Contractor. The Contractor shall have no claim to any payment or compensation whatsoever by reason of or in pursuance of any notice as aforesaid, on account of any suspension, stoppage or curtailment except to the extent specified hereinafter.
(2) Where the total suspension of work ordered as aforesaid continued for a continuous period exceeding 90 days the Contractor shall be at liberty to withdraw from the contractual obligations under the contract so far as it pertains to the unexecuted part of the work by giving a 10 days prior notice in writing to the Managing Director through General Manager, within 30 days of the expiry of the said period of 90 days, of such intention and requiring the Engineer to record the final measurements of the work already done and to pay final bill. Upon giving such notice the Contractor shall be deemed to have been discharged from his obligation to complete the remaining unexecuted work under his contract. On receipt of such notice the Engineer shall proceed to complete the measurement and make such payment as may be finally due to the Contractor within a period of 90 days from the receipt of such notice in respect of the work already done by the Contractor. Such payment shall not in any manner prejudice the right of the Contractor to any further compensation under the remaining provisions of this clause.
(3) Where the Managing Director requires the Contractor to suspend the work for a period in excess of 30 days at any time or 60 days in the aggregate the Contractor shall be entitled to apply to the Managing Director through General Manager and Engineer in-charge within 30 days of the resumption of work after such suspension for payment of compensation to the extent of pecuniary loss suffered by him in respect of working machinery rendered idle on the site or on account of his having had to pay the salary or wages of labour engaged by him during the said period of suspension, provided always that the contractor shall not be entitled to any claim in respect of any such working machinery, salary or wages for the first 30 days whether consecutive or in the aggregate of such suspension or in respect of any suspension whatsoever occasioned by unsatisfactory work or any other default on his part. The decision of the Managing Director in this regard shall be final and conclusive against the Contractor.
(4) In the event of - i) Any total stoppage of work on notice from the STEM under clause (1) in that behalf.
ii) Withdrawal by the Contractor from the contractual obligations to complete the remaining unexecuted work under sub-clause (2) on account of continued suspension of work for a period exceeding 90 days.
OR
iii) Curtailment in the quantity of item or items originally tendered on account of any alteration, omission or substitutions in the specifications drawing, designs, or instructions under clause 14(1) where such curtailment exceeds 25% in quantity and the value of the quantity curtailed beyond 25 percent at the rates for the item specified in the tender is more than Rs. 5,000/-.It shall be open to the Contractor, within 90 daysfrom the service of (i) the notice of stoppage of work or (ii) the notice of withdrawal from the contractual obligations under the contract on account of the continued suspension of work or (iii) notice under clause 15(1) resulting in such curtailment, to produce to the Engineer satisfactory documentary evidence that he had purchased for agreed to purchase material for use in the contract work, before receipt by him of the notice of stoppage, suspension or curtailment and require STEM to take over on payment such material at the rates determined by the STEM, provided, however such rates shall in no case exceeds the rates at which the same were acquired by the Contractor. STEM shall thereafter take over the material so offered, provided the quantities offered, are not in excess of the requirements of the unexecuted work as specified in the accepted tender and are of quality and specifications approved by the STEM.

No claim to any payment or compensation for alteration in or restriction of work.

Clause 15(A):-The Contractor shall not be entitled to claim any compensation from STEM for the loss suffered by him on account of delay by STEM in the supply of materials entered in Schedule A where such delay in caused by – i) Difficulties relating to the supply of railway wagons. ii) Force majeure. iii) Act of God. iv) Act of enemies of the State or any other reasonable cause beyond the control of STEM. In the case of such delay in the supply of materials, STEM shall grant such extension of time for the completion of the works as shall appear to the Managing Director, STEM to be reasonable in accordance with the circumstances of the case. The decision of the Managing Director, STEM as to the extension of time shall be accepted as final by the Contractor.

No claim to compensation on account of loss due to delay in supply of materials by STEM Water Dist. & Infra. Co. Pvt. Ltd.

Clause 16:- Under no circumstances whatever shall the Contractor be entitled to any compensation from STEM on any account unless the Contractor shall have submitted claim in writing to the Managing Director through General Manager and Engineer-in Charge within one month of the case of such claim occurring.

Time limit for unforeseen claims

Clause 17:- If at any time before the security deposit or any part thereof is refunded to the Contractor it shall appear to the Managing Director or General Manager or his subordinate in charge of the work, that any work has been executed with unsound, imperfect or unskilful workmanship or with materials of inferior quality or that any materials or articles provided by him for the execution of the work are unsound or of a quality inferior to the that Contracted for, or are otherwise not in accordance with the Contract, it shall be lawful for the Managing Director through General Manager and Engineer-in-charge to intimate this fact in writing to the Contractor and then notwithstanding the fact that the work, materials or articles complained of may have been inadvertently passed, certified and paid for, the Contractor shall be bound forthwith to rectify, or remove and reconstruct the work so specified in whole or in part, as the case may be require or if so required shall remove the materials or articles so specified and provide other proper and suitable materials or articles at his own charge and cost and in the event of his failing to do so within a period to be specified by the Managing Director through General Manager and Engineer-in-charge in the written intimation aforesaid, the contractor shall be liable to pay compensation at the rate of one percent on the amount of the estimate for every day not exceeding 10 days during which the failure so continuous and in the case of any such failure the General Manager and Engineer-in-charge may rectify or remove and re-execute the work or remove and replace the materials or articles complained of, as the case may be at the risk and expense in all respects of the Contractor. Should the General Manager and Engineer-in-charge consider that any such inferior work or materials as described above may be accepted or made use of it shall be within his discretion to accept the same at such reduce rates as he may fix there for, approval by Managing Director.

Action and compensation payable in case of bad work.

Clause 18:- All works under or in course of execution or executed in pursuance of the contract shall at all times be open to the inspection and supervision of the General Manager and his Engineer, subordinates, and the Contractor shall at all times during the usual working hours, and at all other times at which reasonable notice of the intention of the Managing Director through General Manager and Engineer-in- charge and his subordinates to visit the work shall have been given to the contractor, either himself be present to receive orders and instructions , or have a responsible agent duly accredited in writing present for that purpose. Orders given to the Contractors duly authorized agent shall be considered to have the same force and effect as if they had been given to the Contractor himself.

Work's to be opened to inspection.
Contractor or responsible agent to be present.

Clause 19:-The Contractor shall give not less than five days notice in writing to the General Manager and Engineer-in-charge or his subordinate in charge of the work before covering up or otherwise placing beyond the reach of measurement any work in order that the same may be measured and correct dimension thereof taken before the same is so covered up or placed beyond the reach of measurement and shall not cover up or place beyond the reach of measurement any work without the consent in writing of the General Manager and Engineer- in-charge or his subordinate in charge of the work, and if any work shall be covered up or placed beyond the reach of measurement, without such notice having been given or consent obtained the same shall be uncovered at the Contractors expense, and in default thereof no payment or allowance shall be made for such work or for the materials with which the same was executed.

Notice to be given before work is covered up.

Clause 20:- If during the period of 06 months from the date of completion or as certified by the Engineer-in-charge pursuant to clause-7 of the contract or in the opinion of the Managing Director, STEM the said work is defective in any manner whatsoever, the Contractor shall forthwith on receipt of notice in that behalf from the Managing Director, STEM, duly commence execution and completely carry out at his cost in every respect all the work that may be necessary for rectifying and setting right the defects specified therein including dismantling and reconstruction of unsafe portions strictly in accordance with and in the manner prescribed and under the supervision of the Managing Director, STEM In the event of the Contractor failing or neglecting to commence execution of the said rectification work within the period prescribed there for in the said notice and /or to complete the same as aforesaid as required by the said notice, the Managing Director, STEM may get the same executed and carried out departmentally or by any other agency at the risk, on account and at the cost of the Contractor. The Contractor shall forthwith on demand pay to the STEM the amount of such cost, charges and expenses sustained or incurred by the STEMof which the certificate of the Managing Director, STEM shall be final and binding on the Contractor. Such costs, charges and expenses shall be deemed to be arrears ofland revenue and in the event of the Contractor failing or neglecting to pay the same on demand as aforesaid without prejudice to any other rights and remedies of the STEM, the same may be recovered from the contractor as arrears of land revenue. The STEM shall also be entitled to deduct the same from any amount which may then be payable or which may thereafter become payable by the STEM to the contractor either in respect of the said work or any other work whatsoever or from the amount of security deposit retained by STEM.

Contractor liable for damage done, and for imperfections.

ANNEXURE TO CLAUSE 20 :

The defect liability period shall be as under
Sr Types of WorkDefect liability period after commissioning
I. Head Works :      
a) River Head works including those      
  at storage dams, infiltration galleries,   Five Years  
  trench galleries, bank pitching, intake      
  works, connecting pipe approach      
  bridges etc.      
b) Anicuts or weir Earthen/ Masonary dams   Five Years  
  and ancillary      
c) Nalla/canal Head works inclusive of      
  Infiltration wells, connecting pipes   Three Years  
  production and percolation wells etc.      
d) Tube wells, Bore wells etc.   Three Years  
e) Repair to above (a) to (d) above works   One Years  
II. Pumping Machinery:      
a) Pumping machinery and other allied      
  Mechanical, electrical installation      
  (excluding those provided in treatment      
  plant contract) surge arrestor, water   One Year  
  hammer control devices, chlorinators      
  (excluding those provided in treatment      
  plant.)      
b) Repairs to above (a)   Six Months  
III. Treatment Plants :      
a) Water treatment plant and sewage      
  treatment plant based on contractor’s   Five Years  
  design.      
b) Water treatment plant and sewage      
  Treatment plant based on contractor’s      
  Design based on Dept. design      
c) Repairs to above treatment plant (a) & (b)      
IV. ESR/GSR/BPT/Sump and Pump      
  House etc.      
a) Based on Contractor’s own design   Five Years  
b) Based on departmental design   Three Years  
c) Special Repairs to ESR/GSR/BPT   Two Years  
d) Ordinary repairs to ESR/GSR/BPT/   One Year  
  Sump House etc.      
V. Pipe Lines :      
a) Pumping mains, Gravity mains,      
  Leading mains, including intercepting   Two Years  
  outfall sewer in case of sewerage schemes   One Year  
b) Distribution system, laterals, branch      
  sewers of sewerage system etc.      
c) Repairs to pipeline under (a) & (b)   Two Years  

Clause 21: The Contractor shall supply at his own cost all material (except such special materials, if any as may, in accordance with the contract, be supplied from the Departmental stores), plant, tools appliances, implements, ladders, cordage, tackles, scaffolding and temporary works requisite or proper for the proper execution of the work, whether in the original, altered or substituted from, and whether included in the specification or other documents forming part of the contract or referred to in these conditions or not and which may be necessary for the purpose of satisfying or complying with the requirements of the Engineer- in-charge as to any matter as to which under these conditions he is entitled to be satisfied, or which he is entitled to require together with the carriage therefor to and from the work. The Contractor shall also supply without charge the requisite number of persons with the means and materials necessary for the purpose of setting out works and counting, weighing and assisting in the measurement or examination at any time and from time to time of the work or the materials, failing which the same may be provided by the Engineer-in-charge at the expense of the contractor and the expenses may be deducted from any money due to the Contractor under the contract or from his security deposit or the proceeds of sale thereof, or of sufficient portion thereof. The Contractor shall provide all necessary fencing and lights required to protect the public from accident, and shall also be bound to bear the expenses of defence of every suit, action or other legal proceeding, that may be brought by any person for injury sustained owing to neglect of the above precautions, and to pay any damages and cost which may be awarded in any such suit, action or proceedings to any such person, or which may with the consent of the Contractor be paid for compromising any claim by any such person.

Contractor to supply plant, ladders scaffoldings, etc. And is liable for damages arising from non provisions of lights, fencing etc.

Clause 21(A): The Contractor shall provide suitable scaffolds and working platforms, gangways and stairways and shall comply with the following regulations in connection therewith –
a) Suitable scaffolds shall be provided for workmen for all works that cannot be safely done from a ladder or by other means.
b) A scaffold shall not be constructed, taken down or substantially altered except.
i) Under the supervision of a competent and responsible person; and
ii) As far as possible by competent workers possessing adequate experience in this kind of work.
c) All scaffolds and appliances connected therewith and all ladders shall -
i) Be of sound material.
ii) Be of adequate strength having regard to the loads and strains to which they will be subjected, and
iii) Be maintained in proper condition.
d) Scaffolds shall be so constructed that no part thereof can be displaced in consequence of normal use.
e) Scaffold shall not be over-loaded and so far as practicable the load shall be evenly distributed.
f) Before installing lifting gear on scaffolds special precautions shall be taken to ensure the strength and stability of the scaffolds.
g) Scaffolds shall be periodically inspected by a competent person.
h) Before allowing a scaffold to be used by his workmen the Contractor shall whether the scaffold has been erected by his workmen or not, take steps to ensure that it complies fully with the regulations herein specified.
i) Working platform, gangway, stairways shall -
i) be so constructed that no part thereof can sag unduly on unequally.
ii) be so constructed and maintained, having regard to the prevailing conditions as to reduce as for as practicable risks of persons tripping or slipping and
iii) be kept free from any unnecessary obstruction
j) In the case of working platform, gangways, working places and stairways at a height exceeding 3.00 metres,
i) every working platform and every gangway shall be closely boarded unless other adequate measures are taken to ensure safety,
ii) every working platform and gangway shall have adequate width; and
iii) every working platform and gangway, working place and stairway shall be suitable fenced.
k) Every opening in the floor of a building or in a working platform shall expect for the time and to the extent require to allow the excess of persons or the transport or shifting of material be provided be suitable means to prevent the fall of persons or material.
l) When persons are employed on a roof where there is a danger of falling from a height exceeding 3.00 metres (to be specified) suitable precautions shall be taken to prevent the fall of persons or materials.
m) Suitable precautions shall be taken to prevent persons being struck by articles, which might fall from scaffolds or other working places.
n) Safe means of access shall be provided to all working platforms and other working places.
o) The Contractor/(s) will have to make payments to labourers as per Minimum Wages Act.

Clause 21(B) : The Contractor shall comply with the following regulations as regards the Hoisting Appliances to be used by him :-
a) Hoisting machines and tackles, including their attachments, anchorages and supports shall.
i) be of good mechanical construction, sound material and adequate strength and free from patent defect; and
ii) be kept in good repair and in good working order.
b) Every rope used in hoisting or lowering materials or as a means of suspension shall be of suitable quality and adequate strength and free from patent defect.
c) Hoisting machines and tackles shall be examine and adequately tested after erection on the site and before use and be re-examined in position at intervals to be prescribed by the STEM Water Dist. & Infra. Co. Pvt. Ltd.
d) Every chain, ring, hook, shackle, swivel and pulley block used in hoisting or lowering materials or as a means of suspension shall be periodically examined.
e) Every crane driver or hoisting appliance operator shall be properly qualified.
f) No person who is below the age of 18 years shall be in control of any hoisting machine, including any scaffold, or give signals to the operator.
g) In case of every hoisting machine and of every chain, ring, hook, shackle, swivel and pulley block used in hoisting or lowering or as a means of suspension, the safe working load shall be ascertained by adequate means.
h) Every hoisting machine and all gear referred to in preceding regulation shall be plainly marked with the safe working load.
i) In the case of a hoisting machine having a variable safe working load each safe working load and the conditions under which it is applicable shall be clearly indicated.
j) No part of any hoisting machine or any gear referred to in regulation (h) above shall be loaded beyond the safe working load except for the purpose of testing.
k) Motors, gearing transmissions, electric wiring and other dangerous parts of hoisting appliances shall be provided with efficient safeguards.
l) Hoisting appliances shall be provided with such means as will reduce to a minimum the risk of the accidental descent of the load.
m) Adequate precaution shall be taken to reduce to a minimum the risk of any part of a suspended load becoming accidentally displaced.

Clause 22: The Contractor shall not set fire to any standing jungle, trees, brushwood or grass without a written permit from the STEM When such permit is given, and also in all cases when destroying, cut or dug up trees, brushwood, grass etc. by fire, the Contractor shall take necessary measures to prevent such fire spreading to or otherwise damaging surrounding property. The Contractor shall make his own arrangements for drinking water for the labour employed by him and provide sanitary and other arrangements.

Measure for prevention of fire.

Clause 23: Compensation for all damages done intentionally or unintentionally by Contractors labour whether in or beyond the limits of the STEM property including any damage caused by the spreading of fire mentioned in Clause 22 shall be estimated by the Engineer-in-charge and General Manager subject to the decision of the Managing Director, STEM on appeal shall be final and the Contractor shall be bound to pay the amount of the assessed compensation on demand, failing which the same will be recovered from the Contractor as damage in the manner prescribed in Clause 1 or deducted by the STEM from any sums that may be due or become due from STEM to Contractor under this contract or otherwise. The Contractor shall bear the expenses of defending any action or other legal proceedings that may be brought by any person for injury the spread sustained by him owing to neglect of precautions to prevent the spread of fire and he shall pay any damages and cost that may be awarded by the court in consequence thereof.

Liability of contractor for any damage done in or outside work area.

Clause 24: The employment of female labours on works in neighbourhood of soldiers barracks should be avoided as far as possible.

Employment of female labour

Clause 25: No work shall be done on a Sunday/ Public Holiday without the sanction in writing of the Engineer-in-charge

Work on Sunday

Clause 26: The contract shall not be assigned or sublet without the written approval of the Managing Director/ BoD, and if the Contractor shall assign or sublet his contract, or attempt to do so, or become insolvent or commence any proceedings to get himself adjudicated and insolvent or make any composition with his creditors, or attempt so to do or if bribe, gratuity, gift loan, perquisite, reward or advantage, pecuniary or otherwise shall either directly or indirectly be given, promised or offered by the Contractor or any of his servants or agents to any public officer or person in the employ of STEM in any way relating to his office or employment, or if any such officer or person shall become in any way directly or indirectly interested in the contract, the Managing Director may thereupon by notice in writing rescind the contract, and the security deposit of the Contractor shall thereupon stand forfeited and be absolutely at the disposal of STEM, and the same consequences shall ensure as if the contract had been rescinded under Clause 3 thereof and in addition the Contractor shall not be entitled to recover or be paid for any work therefor actually performed under the contract

Work not to be sublet
Contract may be rescinded and security deposit forfeited for subletting it without approval or for bribing a public officer or if contractor becomes insolvent.

Clause 27: All sums payable by a Contractor by way of compensation under any of these conditions shall be considered as a reasonable compensation to be applied to the use of STEM without reference to the actual loss or damages sustained, and whether any damage has or has not been sustained.

Sum payable by way of compensation to be considered as reasonable compensation without reference to actual loss.

Clause 28: In the case of tender by partners or limited company, any change in the constitution of a firm shall be forthwith notified by the Contractor to the Managing Director through General Manager for his information.

Change in the constitution of firm to be notified.

Clause 29: All works to be executed under the contract shall be executed under the direction and subject to the approval in all respects of the Managing Director, STEM for the time being, who shall be entitled to direct at what point or points and in what manner they are to be commenced, and from time to time carried on.

Direction and control of theManaging Director, STEM

Clause 30(1): Except where otherwise specified in the contract and subject to the powers delegated to him by STEM / BoD under the code, rules, resolutions then in the force, the decision of the Managing Director, STEM for the time being shall be final, conclusive and binding on all parties of the contract upon all questions relating to the meaning of the specifications, designs, drawings and instruction hereinbefore mentioned and as to the quality of workmanship or materials used on the work, or as to any other question, claim right, matter or things whatsoever, if any way arising out of, or relating to the contract, designs, drawings, specifications, estimates , instructions, orders, or other conditions, or otherwise concerning the works, or the execution, or failure to execute the same, whether arising during the progress of the work, or after the completion or abandonment thereof. After completion of work in all respect contractor shall submit final record drawings of executed under this contract dully signed to Managing Director through General Manager and Engineer-in-charge with final bill.

Direction and control of theManaging Director, STEM

Clause 30 (2): The Contractor may within thirty days of receipt by him of any order passed by the Managing Director, STEM as aforesaid appeal against it to the BoD, STEM , concerned with the contract work or project.

Clause 30 (3): If the Contractor is not satisfied with the order passed by the Managing Director, STEM as aforesaid, the Contractor may, within thirty days of receipt by him of any such order appeal against it to the BoD, STEM who, if convinced that Prima-facie the Contractors claim rejected by Managing Director, STEM is not frivolous and that there is some substance in the claim of the Contractor as would merit a detailed examination and decision by the BoD, STEM.

Clause 31 : (Deleted) Stores of European or American manufacture to be obtained from STEM

Clause 32: When the estimate on which a tender is made includes lump sums in respect of part of the work, the Contractor shall be entitled to payment in respect of the items of work involved or the part of the work in question at the same rates as payable under this Contract for each items, or if the parts of the work in question is not in the opinion of the Engineer-in-charge capable of measurement, the Managing Director may at his discretion pay the lump sum amount entered in the estimate and the certificate in writing of the Managing Director shall be final and conclusive against the Contractor with regard to any sum or sums payable to him under the provisions of this clause.
Clause 33: In the case of any class of work for which there is no such specification as is mentioned in Rule 1 of Form B-1 such work shall be carried out in accordance with the Divisional specifications, and in the event of there being no Divisional/ STEM's specification, then in such case the work shall be carried out in all respects in accordance with all instructions and requirements of the Engineer-in-charge through General Manager, approval by Managing Director, STEM.

Lump-sum in estimates.

Clause 34: The expression "Work" or "Works" where used in these conditions, shall unless there be something in the subject or context repugnant to such construction, be constructed to mean the work or works contracted to be executed under or in virtue of the contract, whether temporary or permanent and whether original, altered, substituted or additional.

Definition of work.

Clause 35: The percentage referred to in the tender shall be deducted from/added to the gross amount of the bill before deducting the value of any stock issued.

Contractor’s percentage whether applied to net or gross amount of bill.

Clause 36: All quarry fees, royalties, octroi dues and ground rent for stacking materials, if any, should be paid by the contractor. If the royalty paid challans in government account is not submitted by the contractor, amount of royalty due shall be recovered from contractor’s bill at prevailing rate. Contractor will not be entitled to refund such charges from STEM Water Dist. & Infra. Co. Pvt. Ltd., Thane.

Refund of Quarry fees and royalties.

Clause 37 (A): The Contractor shall be responsible for and shall pay the expenses of providing medical aid to any workmen who may suffer a bodily injury as a result of an accident. If such expenses are incurred by STEM the same shall be recoverable from the Contractor forthwith and be deducted without prejudice to any other remedy of the STEM from any amount due or that may become due to the Contractor.
Clause 37(B): The Contractor shall provide all necessary personal safety equipment and first aid apparatus available for the use of the persons employed on the site and shall maintain the same in condition suitable for immediate use at any time and shall comply with the following regulations in connection therewith :-

a) The workers shall be required to use the equipment’s so provided by the Contractor and the Contractor shall take adequate steps to ensure proper use of the equipment by those concerned.
b) When work is carried on in proximity to any place where there is a risk of drowning all necessary equipment shall be provided and kept ready for use and all necessary steps shall be taken for the prompt rescue of any person in danger.
c) Adequate provision shall be made for prompt first aid treatment of all injuries likely to be sustained during the course of the work.
Clause 37(C): The Contractor shall duly comply with the provisions of "The Apprentices Act. 1961" (III of 1961) the rules made there under and the orders that may be issued from time to time under the said Act and the said Rules and on his failure or neglect to do so he shall be subjected to all the liabilities and penalties provided by the said Act and said Rules.
 

Compensation under workmen's Compensation Act.

ii) The contractor shall engage apprentice such as brick layer, carpenter, wiremen, plumber, as well as blacksmith by recommended by the State Apprenticeship Advisor Director of Technical Education, Dhobi Talaw, Mumbai :400 001.

Clause 38: Excess Quantity: Excess quantity shall be executed only after prior approval of the competent authority granting Administrative Approval to the work and it shall be paid at accepted tender rate only. Contractor shall execute excess quantity only after written approval/ order by the competent Authority/ Managing Director/BOD according to power delegated to them as the case may be. Clause 38-:1) Quantities in respect of the several items shown in the tender are approximate and no revision in the tendered rate shall be permitted in respect of any of the items so long as, subject to any special provision contained in the specifications prescribing a different percentage of permissible variation the quantity of the item does not exceed the tender quantity by more than 25 percent and so long as the value of the excess quantity beyond the limit of tendered quantities at the rate of the item specified in the tender, is not more than Rs.5000/-
ii)The contractor shall, if ordered in writing by the Engineer to do also carry out any quantities in excess or the limit mentioned in sub-clause.
(1) hereof on the same conditions as and in accordance with the specifications in the tender and at the rates
a) derived from the rates entered in the current schedule of rates and in the absence of such rates
b) At the rate prevailing in the market, the said rates being increased or decreased as the case may be by the percentage which the total tendered amount upon the schedule of rates applicable to the year in which the tenders were accepted
For the purpose of operation of this clause, the cost of work shall be worked out from the DSR prevailing at the time of inviting of Tender. The cost of clause 38 is Rs. 2,03,489/-in words (Rupees Two lakh Three Thousand Four Hundred Eighty Nine only) as per D.S.R. 2022 - 2023.
(iii) This clause is not applicable to extra items.
(iv)Claims arising out of reduction in the tendered quantity of any item beyond 25 percent will be governed by the provision of clause 15 only when the amount of such reduction beyond 25 percent at the rate of the item specified in the tender is more than Rs.5000/-. This reduction is exclusively of the reduction mentioned in clause No.14 & 15 of work and site condition.
(v) There is no change in the rate if the excess is less than or equal to 25%. Also there is no change in the rate if quantity of work done is more than 25% of the tendered quantity, but value of the excess work at the tender rates does not exceed Rs.5000/-.
(vi) The quantities to be paid at tendered rate shall include: - Tendered quantity plus. 25% excess of the tendered quantity or the excess quantity of the value of Rs.5000/- at the tendered rate whichever is more.
Clause 38 -A: The Executive engineer shall see that claim towards excess quantity under this clause 38 is submitted to higher authority immediately on its cropping up. The Executive Engineer while making such payment shall see that the total expenditure shall not exceed sanctioned cost of the scheme. If the proposal of Clause 38 is submitted to competent authority for payment then interim 50% payment will be released as under
a) At accepted tender rate or current schedule rate whichever is less subject to condition that total expenditure on the tender shall not exceed sanctioned cost of the scheme
Clause 38 -B:If the rate entered in to schedule B for the work of excavation of pipeline is a combined rate for different strata then the rate entered in Schedule−B will be applicable for quantity 25% in addition to the quantity mentioned in schedule−B of all items of excavation for pipe line trenches and for excess over 25% of Schedule−B quantity ,the rate payable to the contractor shall be worked out from the CSR by considering following percentage of excavation in different strata irrespective of actual strata met at the site for the increased quantity.
1) Excavation in all types of soils,. Sand,gravel and soft murum with lead up to 50 meter and lift as involved. Including dewatering, shoring and strutting etc. excluding refilling etc.% of average rate for lift 0.00 to 1.50 meter and_ % for lift .
2)Excavation in hard murum and boulders with lead up to 50 m and lead and lift as involved including dewatering, shoring and strutting etc. excluding refilling etc._% of average rate for lift meter and %_ for lift_.
3)Excavation in soft rock and old cement and lime masonry with lead upto 50 m and lift as involved, including dewatering, shoring and strutting, excluding refilling etc.% of average rate for liftand% for lift.
4)Excavation in hard rock and concrete road by chiseling wedging line drilling by mechanical means or by all means other than blasting with lead upto 50m and lift as involved, including dewatering, shoring and strutting etc. excluding refilling % of average rate for lift 0.00 to 1.50 m% and 1.50 to 3.00 m

Claim for quantities entered in the tender or estimate.
Quantities put to tender are approximate. Excess quantity beyond quantity put to Tender will be governed as per Cl.38
Payment for average rate of Excavation

Clause 39: The Contractor shall employ any famine, convict or other labour of a particular kind or class if ordered in writing to do so by the Engineer-in-charge.

Employment of famine labour etc.

Clause 40: No compensation shall be allowed for any delay caused in the starting of the work on account of acquisition of land or, in the case of clearance works, on account of any delay in according sanction to estimates.

Claim for compensation for delay in starting of work.

Clause 41: No compensation shall be allowed for any delay in the execution of the work on account of water, standing in borrow pits or compartments. The rates are inclusive for hard or cracked soil, excavation in mud, sub-soil water or water standing in borrows pits and no claim for an extra rate shall be entertained unless otherwise expressly specified.
Clause 42: The Contractor shall not enter upon or commence any portion of work except with written authority and instructions of the Engineer-in- charge or his subordinate in charge of the work. Failing such authority, the Contractor shall have no claim to ask for measurements of the payment for work.

Claim for compensation for delay in execution of work.

Clause 42: The Contractor shall not enter upon or commence any portion of work except with written authority and instructions of the Engineer-in- charge or his subordinate in charge of the work. Failing such authority, the Contractor shall have no claim to ask for measurements of the payment for work.

Entering upon or commencing any portion of work.

Clause 43(i): No contractor shall employ any person who is under the age of 18 years.

Minimum age of persons employed, the employment of donkeys and / or other animals and the payment of fair wages.

(ii) No contractor shall employ donkeys or other animals with breaching of string or thin ropes. The breaching must be at least three inches wide and should be of tape (Nawar).

(iii) No animal suffering from sores, lameness or emaciation or which is immature shall be employed on the work.

(iv) The Engineer-in-charge or his subordinate in charge is authorized to remove from the work, any person or animal found working which does not satisfy these conditions and no responsibility shall be accepted by STEM for any delay caused in the completion of the work by such removal.

(v) The contractor shall pay fair and reasonable wages to the workmen employed by him, in the contract undertaken by him. In the event of any dispute arising between the contractor and his workmen on the grounds that the wages paid are not fair and reasonable, the dispute shall be referred without delay to the Managing Director, STEM through General Manager shall be conclusive and binding on the contractor but such decision shall not in any way affect the conditions in the contract regarding the payment to be made by STEM at the sanctioned tender rates.

(vi) Contractor shall provide drinking water facilities to the workers. Similar amenities shall be provided to the workers engaged on large work in urban areas.

(vii) All facilities provided in the contract labour (Regulation and Abolition Act 1971), The Maharashtra Contract Labour Regulation and Abolition Rule 1971 should be provided.

Clause 44: Payment to contractors shall be made by cheque drawn on any treasury within the division convenient to them, provided the amount exceeds Rs.10. Amounts not exceeding Rs.10 will be paid in cash./As per procedure force in & laid down by STEM

Method of payment.

Clause 45: Any contractor who does not accept these conditions shall not be allowed to tender for works. Entering into contract by the contractor with STEM Water Distri. & Infra. Co. Pvt. Ltd., Thane by the contractor shall be considered as incontrovertible proof of acceptance of all conditions of the contract by the contractor.

Acceptance of conditions compulsory before tendering for work

Clause 46: If Government declares a state of scarcity of famine to exist in any village situated within 10 miles of the work the Contractor shall employ upon such parts of the work, as are suitable for unskilled labour, any person certified to him by the Managing Director, STEM, or by any person to whom the Managing Director, STEM may have delegated this duty in writing to be in need of relief and shall be bound to pay to such person wages not below the minimum which Government may have fixed in this behalf. Any disputes which may arise in connection with the implementation of this clause shall be decided by the Managing Director, STEM whose decision shall be final and binding on the Contractor.

Employment of scarcity labour

Clause 47: The price quoted by the Contractor shall not in any case exceed the control price, if any, fixed by STEM or reasonable price which it is permissible for him to charge a private purchaser for the same class and description of goods under the provision of Hoarding and Profiteering Prevention Ordinance, 1948 as amended from time to time. If the price quoted exceeds the controlled price or the price permissible under Hoarding and Profiteering Prevention Ordinance the Contractor will specifically mention this fact in his tender along with the reasons for quoting such higher prices. The purchaser at his discretion will in such case exercise the right of revising the price at any stage so as to conform with the controlled price on the permissible under the Hoarding and Profiteering Prevention Ordinance. This discretion will be exercised without prejudice to any other action that may be taken against the Contractor.

Price not to exceed controlled price fixed by STEM.

Clause 48: The Bidder shall quote his offer considering all prevailing taxes, cesses, levies, duties, service charge, custom duty etc. excluding Good and Service Tax. No extra payment on this account and due to rise in or new taxes will be made to the contractor.

Rates exclusive of GST.

Clause 49: In case of materials that may remain surplus with the Contractor from those issued for the work contracted for, the date of ascertainment of the materials being surplus will be taken as the date of sale for the purpose of GST and the GST will be recovered on such sale.

GST on surplus materials.

Clause 50: The Contractor shall employ at least 80% of the unskilled labour to be employed by him on the said work from locally available labour and shall give preference to those persons enrolled under Maharashtra Government Employment and Self Employment Department's Scheme. Provided, however, that if the required unskilled labours from that district is are not available locally, the Contractor shall in the first instance employ such number of persons as is available and thereafter may with previous permission, in writing of the Engineer-in-charge of the said work, obtain the rest of requirement of unskilled the labour from outside the above scheme.

Employment of local labour

Clause 51: The contractor shall pay the labourers (skilled and unskilled) according to the wages prescribed by the Minimum Wages Act of 1948 applicable to the area in which the work of the contract is located. The contractor shall comply with the provision of the Apprentices Act, 1961, and the rules and orders issued there under from time to time, if he fails to do so his failure will be a breach of the contract and the Managing Director, STEM, may in his discretion may cancel the contract. The Contractor shall also be liable, for any precautionary liability, arising on account of any violation by him of the provision of Act. The contractor shall pay labourers skilled and unskilled according to the wages prescribed by the Minimum Wages Act, of 1948 applicable to the area in which work lies. The contractor to take precautions against accidents which take place on account of labour using loose garments while working machinery.

Wages to be paid to the skilled & unskilled labour engaged by the Contractor

Clause 52: All amounts whatsoever which the contractor is liable to pay to the STEM Water Distri. & Infra. Co. Pvt. Ltd. in connection with the execution of the work including the amount payable in respect of (i) materials and / or stores supplied/ issued hereunder by the STEM to the contractor. (ii) hire charges in respect of heavy plant, machinery and equipment given on hire, by the STEM Water Distri. & Infra. Co. Pvt. Ltd. to the contractor for execution by him of the work and/or on which advances have been given by the STEM Water Distri. & Infra. Co. Pvt. Ltd. Thane to the contractor.

(iii) excess amount incurred by STEM WaterDistri. & Infra. Co. Pvt. Ltd., Thane over the security deposit furnished by the contractor for completion of work in view of provision of clause 3(b), 3(c) and clause 5(iv). Liquided Damages/ Compensation amount which could not be recovered from the security deposit due to non - availability of adequate Security Deposit to cover such compensation, (v) Penalty under clause 8 so far as the part which could not recovered from any payment due to the collector or from Security Deposit available with Managing Director, (vi) amount of compensation recoverable under clause 17 which could not be recovered from the amount of Security Deposit, (vii) extra expenditure incurre by the STEM for carrying out rectification of defective works under Clause 20, (viii) any other Payment/ compensation/ Penalty/ dues etc. recoverable by the Managing Director from contractor which could not be recovered from the amount of security deposit shall be deemed to be debt payable by the contractor to the STEM Water Distri. & Infra. Co. Pvt. Ltd., Thane and STEM Water distri. & Infra. Co. Pvt. Ltd., Thane without prejudice to any other right and remedies of the STEM Water distri. & Infra. Co. Pvt. Ltd., Thane may recover the same from the contractor as arrears of land revenue through the collector of the District.

Clause 53: The Contractor shall duly comply with all the provisions of the Contract Labour (Regulation and Abolition) Act, 1970 and the Maharashtra Contract Labour (Regulation and Abolition) Rules, 1971 as amended from time to time and all other relevant statutes and statutory provisions concerning payment of wages particularly to workmen employed by the Contractor and working on the site of the work. In particular the Contractor shall pay wages to each worker employed by him on the site of the work at the rates prescribed under the Maharashtra Contract Labour (Regulation and Abolition) Rules, 1971. If the Contractor fails or neglects to pay wages at the said rates or makes short payment and the STEM makes such payment of wages in full or part thereof less paid by the Contractor as the case may be the amount so paid by the STEM to such workers shall be deemed to be an arrears of land revenue and the STEM shall be entitled to recover the same as such from the contractor or deduct the same from the amount payable by the STEM to the Contractor hereunder or from any other amount/s payable to him by the STEM.

Clause 54: i) Where the workers are required to work near machine and are liable to accident they should not be allowed to wear loose cloth like Dhoti, Jhabba etc. ii) The contractor shall engage apprentice such as brick layer, carpenter, wiremen, plumber, as well as blacksmith by recommended by the State Apprenticeship Advisor Director of Technical Education, Dhobi Talaw, Mumbai :400 001.

Clause 55: Provision of all applicable Indian Laws shall be treated as applicable for this contract.

Clause 56: A. The anti malaria and other health measures shall be as directed by the joint Director (Malaria and Filaria) of Health Service, Pune. B. Contractor shall see that mosquitogenic conditions are not created so as to keep vector population to minimum level. C. Contractor shall carry out anti-malaria measures in the area as per guidelines prescribed under National Malaria Eradication Programme and as directed by the Joint Director (M & F) of Health Services, Pune/ Mumbai. D. In case of default in carrying out prescribed anti-malaria measures resulting in increase in malaria incidence, contractor shall be liable to pay to Corporation the amount spent by STEM on anti malaria measures to control the situation in addition to fine.

Conditions for malaria eradication anti malaria and other health measures

Clause 57:The Contractor shall make sufficient arrangements for draining away the sewage water as well as water coming from the bathing and washing places and shall dispose off this water in such a way as not to cause any nuisance. He shall also keep the premises clean by employing sufficient number of sweepers. The Contractor shall comply with all rules, regulations, bye-laws and directions given from time to time by any local or public authority in connection with this work and shall pay fees or charges which are leviable on him without any extra cost of STEM.

Clause 58:The Successful contractor will have to enter in to agreement in form specified by STEM on stamp paper of required amount as per rules inforce. The stamp charges shall be borne by the contractor.

Clause 59: Price Variation Clause(Deleted)

Clause 60: Building and Other Construction Workers Welfare Cess at one percent or at the rates amended from time to time as intimated by the competent authority under Building and Other Constructions Worker Welfare Act 1996 will be deducted from the Bill.

Clause 61:The Contractor shall take out necessary Insurance Policy / Policies viz. Contractor's All Risks Insurance Policy, Erection All Risks Insurance Policy etc. so as to provide adequate insurance cover for execution of the awarded contract work for total contract value and complete contract period including for extended period & up to Defect Liability Period, Compulsorily from the " Directorate of Insurance, Maharashtra State, Mumbai" only. Its postal address for Correspondence is “264, MHADA, First Floor, Opposite Kalanagar, Bandra (East), Mumbai- 400051." Similarly all workmen's appointed to complete the contract work are required to insure under workmen's compensation Insurance Policy. Insurance Policy / Policies taken out from any other company will not be accepted. If any Contractor has not taken out the insurance policy from the “Directorate of Insurance, Maharashtra State, Mumbai” or has effected Insurance with any Insurance Company, the same will not be accepted and 1% of the tender amount or such amount calculated by the STEM & will be recovered directly from the amount payable to the Contractor for the executed contract work and paid required premium to the Directorate of Insurance Fund, Maharashtra State, Mumbai. The Director of Insurance reserves the right to distribute the risks of insurance among the other insurers. Managing Director of STEM is the final authority. for imposition of penalty, fine/ compensation on contractor, if insurance requirements are not complied with by contractor and recover appropriate amount from their bills/ payment dues.

 

Managing Director

STEM Water Dist. & Infra. Co. Pvt. Ltd.,

Thane.











































 

CONDITIONS OF CONTRACT

A. GENERAL

1. Definitions

1.1 Terms which are defined in the Contract Document are not also defined in the Conditions of Contract but keep their defined meanings. Capital initials are used to identify defined terms.

The Adjudicator/ Arbitrator (synonymous with Institutional Arbitration Policy) is 

The person appointed jointly by the STEM and the Contractor to resolve disputes.

Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.(Schedule ‘B’)

The Completion Date is the date of completion of the Works in all respect as certified by the Engineer in-charge and General Manager.

The Contract is the contract between the STEM and the Contractor to execute, complete and maintain the Works. It consists of the documents up to work order & letter to start work.

The Contract Documents defines the documents and other information, correspondence which comprise the Contract.

The Contractor is a person or corporate body whose Bid to carry out the Works has been accepted by the STEM.

The Contractor's Bid is the completed Bidding document submitted by the Contractor to the STEM and includes Technical, Financial bids and further correspondence up to work order.

The Contract Price is the price stated in the Letter of Acceptance, work order and thereafter as adjusted in accordance with the provisions of the Contract.

Days are calendar days; months are calendar months. A Defect is any part of the Works not completed in accordance with the Contract. The Defects Liability Period is the period named in the Contract Data and calculated from the Completion Date.

The STEM is the party who will employ the Contractor to carry out the Works.

The Engineer is the competent person appointed and notified to the contractor to act in replacement of the Engineer) who is responsible for supervising the Contractor, administering the Contract, certifying payments due to the Contractor, issuing and valuing Variations to the Contract, awarding extensions of time, and valuing the Compensation Events.

Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct the Works.

The Initial Contract Price is the Contract Price listed in the STEM Letter of Acceptance and in work order.

The Intended Completion Date is the date on which it is intended that the Contractor shall complete the Works. The Intended Completion Date is specified in the Contract. The Intended Completion Date may be revised only by the Engineer by issuing an extension of time by approval of Competent Authority.

Materials are all supplies, including consumables, used by the contractor for incorporation in the Works.

Plant is any integral part of the Works which is to have a mechanical, electrical, electronic or chemical or biological function.

The Site is the area defined/ stated as such in the Contract Documents.

Site Investigation Reports are those which were included in the Bidding documents and are factual interpretative reports about the surface and sub-surface conditions at the site.

Specification means the Specification of the Works included in the Contract and any modification or addition made or approved by the Competent Authority.

The Start Date is the date when the Contractor shall commence execution of the works. It does not necessarily coincide with any of the Site Possession Dates.

A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a part of the work in the Contract which includes work on the Site.

Temporary Works are works designed, constructed, installed, and removed by the Contractor which are needed for construction or installation of the Works.

A Variation is an instruction given by the competent Authority, which varies the Works.

The Works are what the Contract requires the Contractor to construct, install, and turn over to the STEM, as defined in the Contract Document.

2.0 Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or neuter, and the other way around. Headings have no significance. Words have their normal meaning under the language of the Contract unless specifically defined. The Engineer will provide instructions clarifying queries about the Conditions of Contract.

2.2 If sectional completion is specified in the Contract, references in the Conditions of Contract to the Works, the Completion Date, and the Intended Completion. Date apply to any Section of the Works (other than references to the Completion Date and Intended Completion date for the whole of the Works).

2.3. The documents forming the Contract shall be interpreted in the following order of priority:

(1) Agreement

(2) Letter of Acceptance, work order, notice to proceed with the works

(3) Contractor's Bid, Correspondence between STEM & Bidder.

(4) Contract Data, Undertaking, Affidavits & Forms.

(5) Conditions of Contract including Special Conditions of Contract

(6) Specifications

(7) Drawings

(8) Bill of quantities (Scheduled ‘B’) and

(9) Any other document listed in the Contract Document as forming part & Parcel of

the Contract, including Minutes of Pre- bid meeting etc.



 

3.0 Language and Law

3.1 The language of the Contract and the law governing the Contract are stated in the Contract Documents. Language may be in English or in Marathi for correspondence.

4.0 Engineer's Decisions

4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the STEM and the Contractor in the role representing the STEM.

5.0 Delegation

5.1 The Engineer may delegate any of his duties and responsibilities to other people except to the Adjudicator after notifying the Contractor and may cancel any delegation after notifying the Contractor.

6.0 Communications

6.1 Communications between parties which are referred to in the conditions are effective only when in writing. A notice shall be effective only when it is delivered (in terms of Indian Contract Act).

7.0 Other Contractors

The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities, and the STEM between the dates given in the Schedule of other Contractors. The Contractor shall as referred to in the Contract Document, also provide facilities and services for them as described in the contract. The STEM may modify the schedule of other contractors and shall notify the contractor of any such modification.

8.0 Personnel

8.1 The Contractor shall employ the key personnel as referred to in the Contract Document to carry out the functions stated in the Schedule or other personnel approved by the Engineer. The Engineer will approve any proposed replacement of key personnel only if their qualifications, abilities, and relevant experience are substantially equal to or better than those of the personnel listed.

8.2. If the Engineer asks the Contractor to remove a person who is a member of the Contractor's staff or his work force stating the reasons the Contractor shall ensure that the person leaves the Site within seven days and has no further connection with the work in the Contract.

9.0 STEM and Contractor's Risks

The STEM carries the risks which this Contract states are Employer's risks, and the Contractor carries the risks which this Contract states are Contractor's risks.

10.0     STEM Risks

10.1 The STEM is responsible for the excepted risks which are (a) in so far as they directly affect the execution of the Works in India, the risks of war, hostilities, invasion, act of foreign enemies, rebellion, revolution, insurrection or military or usurped power, civil war, riot commotion or disorder (unless restricted to the Contractor's employees), and contamination from any nuclear fuel or nuclear waste or radioactive toxic explosive, or (b) a cause due solely to the design of the Works, other than the Contractor's design.


 

11.0 Contractor's Risks

All risks of loss of or damage to physical property and of personal injury and death which arise during and in consequence of the performance of the Contract other than the excepted risks are the responsibility of the Contractor.

12.0 Insurance

12.1 The Contractor shall provide, in the joint names of the STEM and the Contractor, insurance cover from the Start Date to the end of the Contract Period including extension period and up to DLP, in the amounts and deductibles stated in the Contract Documents for the following events which are due to the Contractor's risks:

(a) loss of or damage to the Works, Plant and Materials;

(b) loss of or damage to Equipment’s:

(c) loss of or damage of property in connection with the Contract; and

(d) personal injury or death.

12.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the Engineer's approval before the Start Date. All such insurance shall provide for compensation to be payable in the types and proportions of currencies required to rectify the loss or damage incurred.

12.3 If the Contractor does not provide any of the policies and certificates required, the STEM may affect the insurance which the Contractor should have provided and recover the premiums the STEM has paid from payments otherwise due to the Contractor or, if no payment is due, the payment of the premiums shall be a debt due.

12.4 Alterations to the terms of an insurance shall not be made without the approval of the Competent Authority.

12.5 Both parties shall comply with any conditions of the insurance policies.

12.6 Managing Director of STEM is the final Authority for imposition of penalty, fine /compensation on contractor, if above insurance requirements are not complied with by the contractor & recover appropriate amount from their bills/Payment dues.

13.0 Site Investigation Reports

The Contractor, in preparing the Bid, shall rely on any site Investigation Reports referred to in the Contract Documents, supplemented by any information available to the Bidder.

14.0 Queries about the Contract Data/ Document.

14.1 Managing Director will clarify queries on the Contract Document.

15.0 Contractor to Construct the Works

15.1 The Contractor shall construct and install the Works in accordance with the Specification and Drawings.

16.0 The Works to be completed by the Intended Completion Date

16.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the Works in accordance with the program submitted by the Contractor, as updated with the approval of the General Manager and Managing Director, and complete them by the Intended Completion Date.

 

17.0 Approval by the Engineer

17.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to the Engineer, who is to approve them if they comply with the Specifications and Drawings.

17.2 The Contractor shall be responsible for design of Temporary Works.

17.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the Temporary Works.

17.4 The Contractor shall obtain approval of third parties to the design of the Temporary Works where required.

17.5 All Drawings prepared by the Contractor for the execution of the permanent Works, are subject to prior approval by the General Manager and Managing Director before their use.

18.0 Safety

18.1 The Contractor shall be responsible for the safety of all activities on the Site.

19.0 Discoveries

19.1. Anything of historical or other interest or of significant value unexpectedly discovered on the Site is the property of the STEM. The Contractor is to notify the Engineer of such discoveries and carry out the Engineer's instructions for dealing with them.

20.0 Possession of the Site

20.1 The STEM shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract the STEM is deemed to have delayed the start of the relevant activities and this will be Compensation event.

21.0 Access to the Site

21.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site, to any place where work in connection with the Contract is being carried out or is intended to be carried out and to any place where materials or plant are being manufactured / fabricated / supply/ erection/ commissioning/ Testing/ assembled for the works.

22.0 Instructions

22.1 The Contractor shall carry out all instructions of the Engineer pertaining to works which comply with the applicable laws where the Site is located.

22.2 The Contractor shall permit the STEM to inspect the Contractor's accounts and records relating to the performance of the Contractor and to have them audited by audit or sappointed by the STEM, if so required by the STEM.

23.0 Disputes

23.1 If the Contractor believes that a decision taken by the Engineer in-Charge was either outside the authority given to the Engineer in-Charge by the Contract or that the decision was wrongly taken, the decision shall be referred to the Managing Director/ BoD STEM within 14days of the notification of the General Manager decision.


 

B. TIME CONTROL

24.0 Programme

24.1 Within the time stated in the Contract Document the Contractor shall submit to the Engineer in-Charge for approval a Programme showing the general methods, arrangements, order, and timing for all the activities in the Works along with monthly cash flow forecast.

24.2 An update of the Programme shall be a programme showing the actual progress achieved one ach activity and the effect of the progress achieved on the timing of the remaining work including any changes to the sequence of the activities.

24.3 The Contractor shall submit the Engineer, for approval, an updated Programme at intervals no longer than the period stated in the Contract Document. If the Contractor does not submit an updated Programme within this period, the Engineer in-Charge may withhold the appropriate amount from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Programme has been submitted.

24.4. The Engineer in-Charge and General Manager approval of the Programme shall not alter the Contractor's obligations. The Contractor may revise the Programme and submit it to the Engineer in-Charge again at any time. A revised Programme is to show the effect of Variations and Compensation Events for approval of General Manager and Managing Director.

25.0 Extension of the Intended Completion Date

25.1 The Engineer in-Charge and General Manager after approval of Managing Director/ Competent Authority shall extend the Intended Completion Date if a Compensation Event occurs or a Variation is issued which makes it impossible for Completion to be achieved by the Intended Completion Date without the Contractor taking steps to accelerate the remaining work.

25.2 The Engineer in-Charge and General Manager shall decide whether and by how much to extend the Intended Completion Date within 35 days of the Contractor asking the Engineer in-Charge for a decision upon the effect of a Compensation Event or Variation and submitting full supporting information. If the Contractor has failed to give early warning of a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing the new Intended Completion Date.

25.3 The Engineer in-Charge and General Manager shall within 14 days of receiving full justification from the contractor for extension of Intended Completion Date refer to the Employer (STEM- Managing Director) his decision.

26.0 Delays Ordered by the Engineer

26.1 The Engineer in-Charge and General Manager may instruct the Contractor to delay the start or progress of any activity within the Works.

26.2 In case of non- availability of land or any other valid reasons, the time limit extension shall be granted by the competent authority, on recommendations of Engineer in-Charge and General Manager .

27.0 Management Meetings

27.1 Either the Engineer in-Charge and General Manager or the Contractor may require the other to attend a management meeting. The business of a management meeting shall be to review the plans for remaining work and to deal with matters raised in accordance with the early warning procedure.

27.2 The Engineer in-Charge and General Manager shall record the business of work management meetings and is to provide copies of his record to those attending the meeting and to the STEM. The responsibility of the parties for actions to be taken is to be decided by the Engineer in-Charge and General Manager either at the work management meeting or after the management meeting and stated in writing to all who attended the meeting.

28.0 Early Warning

28.1 The Contractor is to warn the Engineer in-Charge and General Manager at the earliest opportunity of specific likely future events or circumstances that may adversely affect the quality of the work, increase the Contract Price or delay the execution of works. The Engineer in-Charge may require the Contractor to provide an estimate of the expected effect of the future event or circumstance on the Contract Price and Completion Date. The estimate is to be provided by the Contractor as soon as reasonably possible.

28.2 The Contractor shall cooperate with the Engineer in-Charge and General Manager in making and considering proposals for how the effect of such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying out any resulting instruction of the Engineer in-Charge and General Manager.

C. QUALITY CONTROL

29.0 Identifying Defects

29.1 The Engineer in-Charge shall check the Contractor's work and notify the Contractor of any Defects that are found. Such checking shall not affect the Contractor's responsibilities. The Engineer in-Charge may instruct the Contractor to search for a Defect including manufacturing defects of equipment’s supplied material used for works and to uncover and test any work that the Engineer in-Charge and General Manager considers may have a Defect.

30.0 Tests

If the Engineer in-Charge and General Manager instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and any samples.

31.0 Correction of Defects

31.1 The Engineer in-Charge and General Manager shall give notice to the Contractor of any Defects before the end of the Defects Liability Period, which begins at Completion and is defined in the Contract Document. The Defects Liability Period shall be extended for as long as Defects remain to be corrected.

31.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length of time specified by the Engineer in-Charge and General Manager notice.

32.0 Uncorrected Defects

32.1 If the Contractor has not corrected a Defect within the time specified in the Engineer in-Charge and General Manager notice, the Engineer in-Charge and General Manager will assess the cost of having the Defect corrected, and the Contractor will pay this amount/will be recovery from contractor.

32.2 Defects Liability Period for all works executed under this contract agreement is 6 (Six) months from the final date of completion of work in all respect reported in final bill.

 

32.3 During the Defects Liability Period concern Engineer in-Charge and General Manager shall inspect the work twice in a year (Before monsoon & after monsoon) and submit report through concern General Manager with his comments to Managing Director. If defects are found during the said inspection Engineer in-Charge and concern General Manager intimation to contractor in constructing to rectify the said defects / re-construct new work if required and get the work done within Three (3) months and report accordingly to General Manager. If there is any dispute on this issue concern General Manager shall submit his report with his comments to Managing Director accordingly for decision.


 

D. COST CONTROL

33.0 Bill of Quantities

33.1 The Bill of Quantities (Scheduled ‘B’) shall contain items for the construction, installation, testing, and commissioning work to be done by the Contractor.

33.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of the work done at the rate in the Bill of Quantities for each item.

33.3 If the quantity stated in the tender exceed the tender quantity, during execution (i.e. excess quantity), the Managing Director shall obtain approval for excess quantity involved from the Board of Director (for revised Administrative & Financial Approval) OR By Managing Director according to power delegated to them as the case may be.

33.4 Payment of excess quantity will be made after approval of revised Administrative approval by competent authority if required. Contractor shall execute excess quantity only after written approval/ order by the Engineer- in- charge and General Manager with item wise quantity and rates. Rates applicable to excess quantity shall be at the rate of accepted tender rates only. No rise in rates in any case shall be admissible.

33.5 It is binding on the contractor to carry out such extra works as will be occurred when the same can be conveniently carried out by the contractor in the opinion of the Engineer-in-Charge and General Manager & ordered in writing after approval of competent authority with terms as internal part of the main work in addition, alteration or legitimate and reasonable extension. Extra charges of claims in respect of extra works shall not be allowed unless the work to which they relate are clearly without the spirit and meaning the specifications or unless such works are ordered in writing by Engineer-in-Charge after approval of Competent Authority or his representative and claimed for in specified manner before the work is taken in hand.

34.0 Cash Flow Forecasts

34.1 When the Programme is updated, the contractor is to provide the Engineer-in-Charge and General Manager with an updated cash flow forecast.

35.0 Payment Certificates

35.1 The Contractor shall submit to the Engineer-in-Charge and General Manager monthly statements of the estimated value of the work completed less the cumulative amount certified previously.

35.2. The Engineer-in-Charge and General Manager shall check the Contractor's monthly statement within 7 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts.

35.3. The value of work executed shall be determined by the Engineer-in-Charge and General Manager.

35.4. The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed.

35.5 The value of work executed shall include the valuation of Variations and Compensation Events.

35.6. The Engineer-in-Charge and General Manager may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.

36.0 Payments

36.1. Payments shall be adjusted for deductions for advance payments, retention, other recoveries in terms of the contract and taxes at source, as applicable under the law. The bill shall be paid after due verification and upon availability of budget/fund. No interest on outstanding Payment/ Bill shall be admissible.

36.2. Items of the Works for which no rate or price has been entered in will not be paid for by the STEM and shall be deemed covered by other rates and prices in the Contract.

36.3 Mobilization Advance, Secured Advance, Work done but not measured Advance or any other type of Advance payment under this contract agreement is not admissible / will not be paid under this contract under any circumstances.

37.0 Compensation Events

37.1 Compensation shall be applicable and only extension may be considered on merits if not on part of Contractor

37.2 The Contractor shall not be entitled to compensation to the extent that the STEM interests are adversely affected by the Contractor not having given early warning or not having cooperated with the Engineer-in-Charge and General Manager.

38.0 Tax

38.1 The rates quoted by the Contractor shall be deemed to be exclusive of the GST sales and other taxes, duties, cess etc., that the Contractor will have to pay for the performance of this Contract. The STEM will perform such duties in regard to the deduction of such taxes at source as per applicable law.

39.0 Currencies

39.1 All payments shall be made in Indian Rupees.

40.0 Retention

40.1 The STEM shall retain from each payment due to the Contractor the proportion stated in the Contract Document until Completion of the whole of the Works.

40.2 On Completion of the whole of the Works total amount retained is repaid to the Contractor after contract Period has passed and the Engineer-in-Charge and General Manager has certified that all the works completed as per specification of contract document.

41.0 Liquidated Damages

41.1 The Contractor shall pay liquidated damages to the STEM at the rate per day stated in the Contract Document for each day that the Completion Date is later than the Intended Completion Date (for the whole of the works or the milestone as stated in the contract Document i.e. for slow progress form contractor’s side). The total amount of liquidated damages shall not exceed the amount defined in the Contract Document. The STEM may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages does not affect the Contractor's liabilities.

41.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer-in-Charge and General Manager shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate.

41.3. If the contractor fails to comply with the time for completion as stipulated in the tender, then the contractor shall pay to the STEM the relevant sum stated in the Contract Document as Liquidated damages for such default and not as penalty for everyday or part of day which shall elapse between relevant time for completion and the date stated in the taking over certificate of the whole of the works on the relevant section, subject to the limit stated in the contract document.

The STEM may, without prejudice to any other method of recovery deduct the amount of such damages from any monies due or to become due to the contractor. The payment or deduction of such damages shall not relieve the contractor from his obligation to complete the works on from any other of his obligations and liabilities under the contract.

41.4. If, before the Time for Completion of the whole of the Works or, if applicable, any Section, a Taking - Over Certificate has been issued for any part of the Works or of a Section, the liquidated damages for delay in completion of the remainder of the Works or of that Section shall, for any period of delay after the date stated in such Taking-Over Certificate, and in the absence of alternative provisions in the Contract, be reduced in the proportion which the value of the part so certified bears to the value of the whole of the Works or Section, as applicable. The provisions of this Sub-Clause shall only apply to the rate of liquidated damages and shall not affect the limit thereof.

42.0 Securities

42.1 The Performance Security (including additional security for unbalanced bids) shall be provided to the STEM no later than the date specified in the Letter of Acceptance and shall be issued in an amount and form and by a bank or surety acceptable to the STEM, and denominated in Indian Rupees. The Performance Security and additional security for unbalanced bids shall be valid until a date 28 days from the date of issue of the certificate of completion.

43.0 Cost of Repairs

43.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and the end of the Defects Correction periods shall be remedied by the Contractor at the Contractor’s cost if the loss or damage arises from the Contractor's acts or omissions.

E. FINISHING THE CONTRACT

44.0 Completion

44.1 The Contractor shall request the Engineer-in-Charge and General Manager to issue a Certificate of Completion of the Works and the Engineer-in-Charge and General Manager will do so upon deciding that the Work is completed in all respect.

45.0 Taking Over

45.1 The STEM shall take over the Site and the Works with final record drawing of executed work within seven days of the Engineer-in-Charge and General Manager issuing a certificate of Completion.

46.0 Final Account

46.1. The Contractor shall supply to the Engineer-in-Charge and General Manager a detailed account of the total amount that the Contractor considers payable under the Contract before the end of the Defects Liability Period. The Engineer-in-Charge and General Manager shall issue a Defect Liability Certificate and certify any final payment that is due to the Contractor within 56 days of receiving the Contractor's account if it is correct and complete. If it is not, the Engineer-in-Charge and General Manager shall issue within 56 days a schedule that states the scope of the corrections or additions that are necessary. If the Final Account is still unsatisfactory after it has been resubmitted, the Engineer-in-Charge and General Manager shall decide on the amount payable to the Contractor and issue a payment certificate, within 56 days of receiving the Contractor’s revised account.

47.0 Operating and Maintenance Manuals-

47.1 If "as built" Drawings and/or operating and maintenance manuals are required, the Contractor shall supply them by the dates stated in the Contract Documents.

47.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract Document, or they do not receive the Engineer-in-Charge and General Manager / Competent Authorities’ approval, the Engineer-in-Charge and General Manager shall withhold the amount stated in the Contract Document from payments due to the Contractor.

48.0 Termination

48.1 The STEM or the Contractor may terminate the Contract if the other party causes a fundamental breach of the Contract.

48.2 Fundamental breaches of Contract include, but shall not be limited to the following:

(a) the Contractor stops work for 15 days when no stoppage of work is shown on the current Programme and the stoppage has not been authorized by the Engineer-in-Charge and General Manager;

(b) the Engineer-in-Charge and General Manager  instructs the Contractor to delay the progress of the Works and the instruction is not withdrawn within 28 days;

(c) the STEM or the Contractor is made bankrupt or goes into liquidation other than for a reconstruction or amalgamation;

(d)  the Engineer-in-Charge and General Manager  gives Notice that failure to correct a particular Defect is a fundamental breach of Contract and the Contractor fails to correct it within a reasonable period of time determined by the Engineer-in-Charge and General Manager ;

(e) the Contractor does not maintain a security which is required;

(f) the Contractor has delayed the completion of works by the number of days for which the maximum amount of liquidated damages can be paid as defined in the Contract data; and

(g) if the Contractor, in the judgment of the STEM has engaged in corrupt or fraudulent practices in competing for or in executing the Contract.

For the purpose of this paragraph: "corrupt practice" means the offering, giving, receiving or soliciting of anything of value to influence the action of a public official in the procurement process or in contract execution. "Fraudulent practice" means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to the detriment of the Borrower, and includes collusive practice among Bidders (prior to or after bid submission) designed to establish bid prices at artificial non-competitive levels and to deprive the Borrower of the benefits of free and open competition."

48.3 When either party to the Contract gives notice of a breach of contract to the Engineer-in-Charge and General Manager for a cause other than those listed under Sub Clause above, the Engineer-in-Charge and General Manager shall decide whether the breach is fundamental or not.

48.4 Notwithstanding the above, the STEM may terminate the Contract for convenience.

48.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe and secure and leave the Site, Soon as reasonably possible.

49.0 Payment upon Termination

49.1 If the-Contract is terminated because of a fundamental breach of Contract by the Contractor, the Engineer-in-Charge and General Manager shall issue a certificate for the value of the work done less advance payments received up to the date of the issue of the certificate, less other recoveries due in terms of the contract, less taxes due to be deducted at source as per applicable law and less the percentage to apply to the work not completed as indicated in the Contract Document. If the total amount due to the STEM exceeds any payment due to the Contractor the difference shall be a debt payable to the STEM.

49.2 If the Contract is terminated at the STEM  convenience or because of a fundamental breach of Contract by the STEM, the Engineer-in-Charge and General Manager shall issue a certificate for the value of the work done, the cost of balance material brought by the contractor and available at site, the reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely on the Works, and the Contractor's costs of protecting and securing the Works and less advance payments received up to the date of the certificate, less other recoveries due in terms of the contract and less taxes due to be deducted at source as per applicable law.

50.0 Property

50.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the property of the STEM, if the Contract is terminated because of a Contractor’s default and balance work is to be carried at the risk & cost of the contractor.

51.0 Releases from Performance

If the Contract is frustrated by the outbreak of war or by any other event entirely outside the control of either the Employer or the Contractor the Engineer-in-Charge and General Manager shall certify that the Contract has been frustrated. The Contractor shall make the Site safe and stop work as quickly as possible after receiving this certificate and shall be paid for all work carried out before receiving it and for any work carried out afterwards to which commitment was made.

F. CONDITIONS OF CONTRACT REGARDING LABOUR

52.1 LABOUR:

The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the engagement of all staff and labour, local or other, and for their payment, housing, feeding and transport. The Contractor shall, if required by the Engineer-in-Charge and General Manager, deliver to the Engineer-in-Charge and General Manager a return in detail, in such form and at such intervals as the Engineer-in-Charge and General Manager may prescribe, showing the staff and the numbers of the several classes of labour from time to time employed by the Contractor on the Site and such other information as the Engineer-in-Charge and General Manager may require.



 

52.2 COMPLIANCE WITH LABOUR REGULATIONS:

During continuance of the contract, the Contractor and his sub-contractors shall abide at all times by all existing labour enactments and rules made there under, regulations, notifications and bye laws of the State or Central Government or local authority and any other labour law (including rules), regulations, bye laws that may be passed or notification that may be issued under any labour law in future either by the State or the Central Government or the local authority. Salient features of some of the major labour laws that are applicable to construction industry are given below. The Contractor shall keep the STEM indemnified in case any action is taken against the STEM by the competent authority on account of contravention of any of the provisions of any Act or rules made there under, regulations or notifications including amendments. If the STEM is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for non-observance of the provisions stipulated in the notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the part of the Contractor, the Engineer-in-Charge and General Manager /STEM shall have the right to deduct any money due to the Contractor including his amount of performance security. The STEM/ Engineer-in-Charge and General Manager shall also have right to recover from the Contractor any sum required or estimated to be required for making good the loss or damage suffered by the STEM.

The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the STEM at any point of time.

SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO ESTABLISHMENTSENGAGED IN BUILDING AND OTHER CONSTRUCTIONWORK.

(a) Workmen Compensation Act 1923 :- The Act provides for compensation in case of injury by accident arising out of and during the course of employment.

(b) Payment of Gratuity Act 1972 :- Gratuity is payable to an employee under the Act on satisfaction of certain conditions on separation if an employee has completed 5 years service or more on death, the rate of 15 days wages for every completed year of service. The Act is applicable to all establishments employing 10 or more employees.

(c) Employees P.P. and Miscellaneous Provision Act 1952:The Act Provides for monthly contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are: (i) Pension or family pension on retirement or death, as the case may be. (ii) Deposit linked insurance on the death in harness of the worker. (iii) Payment of P.P. accumulation on retirement/death etc.

(d) Maternity Benefit Act 1951:- The Act provides for leave and some other benefits to women employees in case of confinement or miscarriage etc.

(e) Contract Labour (Regulation & Abolition) Act 1970:- The Act provides for certain welfare measures to be provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are required to be provided, by  as the Principal Employer by Law. The Principal Employer is required to take Certificate of Registration and the Contractor is required to take licence from the designated Officer. The Act is applicable to the establishments or Contractor, if they employ 20 or more contract labour.

(f) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the Minimum Wages fixed by appropriate Government as per provisions of the Act, if the employment is a scheduled employment. Construction of Buildings, Roads, Runways are scheduled employments.

(g) Payment of Wages Act 1936:- Itlays down as to by what date the wages are to be paid, when it will be paid and what deductions can be made from the wages of the workers.

(h) Equal Remuneration Act 1979 :- The Act provides for payment of equal wages for work of equal nature to Male and Female workers and for not making discrimination against Female employees in the matters of transfers, training and promotions etc.

(i) Payment of Bonus Act 1965 :- The Act is applicable to all establishments employing 20 or more employees. The Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and maximum of 10% of wages to employees drawing Rs.3500/-per month or less. The bonus to be paid to employees getting Rs.2500/- per month or above upto Rs.3500/- per month shall be worked out by taking wages as Rs.2S00/ -per month only. The Act does not apply to certain establishments. The newly set-up establishments are exempted for five years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of this Act.

(j) Industrial Disputes Act 1947 :- The Act lays down the machinery and procedure for resolution of Industrial disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or retrenching the employees or closing down the establishment.

(k) Industrial Employment (Standing Orders) Act 1946 :-It is applicable to all establishments employing100 or more workmen (employment size reduced by some of the States and Central Government to SO). The Act provides for laying down rules governing the conditions of employment by the Employer on matters provided in the Act and get the same certified by the designated Authority.

(l) Trade Unions Act 1926 :- The Act lays down the procedure for registration of trade unions of workmen and employers. The Trade Unions registered under the Act have been given certain immunities from civil and criminal liabilities.

(m) Child Labour (Prohibition & Regulation) Act 1986 :- The Act prohibits employment of children below14 years of age in certain occupations and processes and provides for regulation of employment of children in all other occupations and processes. Employment of Child Labour is prohibited in Building and Construction Industry. (n) Inter-State Migrant workmen's (Regulation of Employment &Conditions of Service) Act 1979 :- The Act is applicable to an establishment which employs 5 or moreinter-state migrant workmen through an intermediary (who has recruited workmen in one state for employment in the establishment situated in another state). The Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be provided certain facilities such as housing, medical aid, travelling expenses from home up to the establishment and back, etc.

(o) The Building and Other Construction workers (Regulation of Employment and Conditions of Service)Act 1996 and the Cess Act of 1996 :- All the establishments who carryon any building or other construction work and employs 10 or more workers are covered under this Act. All such establishments are required to pay cess at the rate not exceeding 2% of the cost of construction as may be modified by the Government. The Employer of the establishment is required to provide safety measures at the Building or construction work and other welfare measures, such as Canteens, First-Aid facilities, Ambulance, Housing accommodations for workers near the work place etc. The Employer to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

(p) Factories Act 1948:- The Act lays down the procedure for approval of plans before setting up a factory, health and safety provisions, welfare provisions, working hours, annual earned leave and rendering information regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing 10 persons or more with aid of power or 20 or more persons without the aid of power engaged in manufacturing process.


 

       Managing Director

STEM Water Dist. & Infra. Co. Pvt. Ltd.,

    Thane.

GENERAL CONDITIONS OF CONTRACT

  1. Content of Bidding Documents
  1. The set of bidding documents comprises the documents listed below and addenda issued.

Section

Particular

1

Invitation for Bids

2

Instruction to Bidders (DTN)

3

Qualification information and other forms (Pre & Post)

4

Conditions of Contract, Undertakings, Affidavits.

5

Contract Data

6

Technical Specifications

7

Form of Bid

8

Bill of Quantities

9

Other forms, Minutes of Pre bid Meeting (if any)

10

Drawings

11

Documents to be furnished by bidder, D.D./F.D.R/B.G.

The bidder is expected to examine carefully all instructions, conditions of contract, Pre- qualification criteria/ Post qualification criteria, contract data, forms, terms, technical specifications, bill of quantities, forms, Annexes and drawings in the Bid Document. Failure to comply with the requirements of Bid Documents shall be at the bidder's own risk.

  1. Clarification of Bidding Documents (If Pre- bid is applicable)
  1. A prospective bidders requiring any clarification of the bidding documents may notify the STEM in writing or by Fax /email at the Employer’s (STEM’s) address indicated in the invitation to bid before the date and time of the pre-bid meeting specified in the Tender Schedule. The Employer will respond& uploaded to any request for clarification which he received, earlier than 3 days prior to the Bid due date, viewable to all tenderer, including a description of the enquiry but without identifying its source.
  2. Pre-bid meeting (Applicable for works over Rs. 1.50 Crores only)
  1. The bidder or his official representative is invited to attend a pre-bid meeting which will take place at the     address, venue, time and date as indicated in NIT.
  2. The purpose of the meeting will be to clarify issues and to answer questions on any matter that may be raised at that stage.
  3. The bidder is requested to submit any questions in writing by fax or by e-mail to reach the STEM well   before the date & time of the pre-bid meeting, at least one day before pre- bid.
  4. Minutes of the meeting, including the text of the questions raised (without identifying the source of enquiry) and the responses given will be transmitted by uploading on e-tender portal without delay for information to all intended bidder. Any modifications of the bidding documents listed which may become necessary as a result of the pre-bid meeting shall be made by the STEM exclusively through the issue of an Addendum and the minutes of the pre-bid meeting only. Minutes, clarifications, Addendum shall be the part and parcel of the accepted tender.
  5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
  1. Amendment of Bidding Documents
  1. Before the deadline for submission of bids, the STEM may modify the bidding documents by issuing addendum. 
  2. Any addendum thus issued shall be part of the bidding documents and shall be communicated in writing or by fax or e-mail to all the purchasers of the bidding documents. Prospective bidders shall acknowledge receipt of each addendum in writing or by fax or email to the Employer (STEM). The STEM will assume no responsibility for postal delays.
  3. To give prospective bidders reasonable time in which to take an addendum into account in preparing their bids, the STEM may, at his discretion, extend as necessary the deadline for submission of bids.
  1. PREPARATION OF BIDS
  1. Language of the Bid

            All documents relating to the bid shall be in the English language.

  1. Documents Comprising the Bid

            The bid to be submitted by the bidder shall be in two separate parts:

Part I shall be named "Technical Bid" and shall comprise (Envelop No. 1)

  1. Bid Security in the form specified.
  2. Qualification Information and supporting documents as specified. 
  3. Certificates, undertakings, affidavits as specified.
  4. Any other information pursuant to instructions, Registration, experience certificate, PAN, GSTN etc. 
  5. Undertaking that the bid shall remain valid for the period specified. 
  6. Other documents, PoA, Partnership deed, constitution or Legal status of bidder.

Part II shall be named "Financial Bid" and shall comprise (Envelop No. 2)

  1. Form of Bid a specified. (% above/below to the estimated cost put to tender).
  2. Priced Bill of Quantities for items specified. (When item wise rates called for).

Each part will be separately sealed and marked in accordance with the Sealing and Marking Instructions.

  1. Bid Prices.
  1. The contract shall be for the whole works as described in, based on the priced Bill of Quantities submitted by the Bidder. For B1 it be % rate basis.
  2. The bidder shall fill rates and prices and line item total (both in figures and words) for all items of the Works described in the Bill of Quantities along with total bid price (both in figures and words). Items for which no rate or price is entered by the bidder will not be paid for by the Employer when executed and shall be deemed covered by the other rates and prices in the Bill of Quantities. Corrections of any, shall be made by crossing out, initialling, dating and rewriting. For B1 it be% rate basis.
  3. All duties, taxes and other levies payable by the contractor under the contract, or for any other cause shall be included in the rates, prices and total Bid Price submitted by the Bidder. The Tendered rate / quoted rates shall be inclusive of all taxes, duties , levies, cess, Royalties (including Goods & Service Taxes (GST), Sales Tax, Service Tax, any other taxes, custom Duty, Excise Duty, any other Duties, VAT, Income Tax, Work Contract Tax, Stamp duty, LBT, Octroi etc.) as amended time to time & TDS to that effect applicable time to time. No extra / separate payment on this account shall be made / admissible to the Bidder / contractor. Rise in rate of any type of taxes and duties or new taxes, Duties and cess imposed by Govt., after quoting offer are also not admissible for reimbursement. 1% of actual value of work done will be deducted as a Labourcess from each bill under the provisions of Building and Other Construction Works Welfare Act 1996. Bidder shall quote his offer accordingly. 
  4. The rates and prices quoted by the bidder shall be fixed for the duration of the Contract and shall not be    subject to adjustment on any account.
  5. The unit rates and the Prices shall be quoted by the bidder entirely in Indian Rupees. All payment shall be made in Indian Rupees.
  6. Bid Validity
  1. Bids shall remain valid for a period not less than 60 days after the deadline date for bid submission specified. A bid valid for a shorter period shall be rejected by the STEM as non-responsive. In case of discrepancy in bid validity period between that given in the undertaking and the Form of Bid submitted by the bidder, the latter shall be deemed to stand corrected in accordance with the former and the bidder has to provide for any additional security that is required.
  2. In exceptional circumstances, prior to expiry of the original validity, the STEMmay request that the bidders may extend the period of validity for a specified additional period. The request and the bidders' responses shall be made in writing or by cable. A bidder may refuse the request without forfeiting his bid security. A bidder agreeing to the request will not be required or permitted to modify his bid, but will be required to extend the validity of his bid security for a period of the extension.
  3. The Bidder shall prepare one original and one copy of the documents comprising the bid as described in Clause 12 of these Instructions to Bidders, bound with the volume containing the "Technical Bid" and "Financial Bid" in separate parts and clearly marked "ORIGINAL" and "COPY" as appropriate. In the event of discrepancy between them, the original shall prevail. Within 72 Hrs. from the last date & time of submission of tender /Bid (BIDLOCK TIME). Bidder / Contractor shall be submit a sealed “HARD COPY” of Bid (Envelop No.1& Envelop No.2 separately) to Head Office.(To Accountant or Accounts Officer or Managing Director). However non- submission of Hard copy is not constitute a bar to open e- offer’s. 
  4. The original and copy of the Bid shall be typed or written in indelible ink and shall be signed by a person or persons duly authorized to sign on behalf of the Bidder. All pages of the bid where entries or amendments have been made shall be initialed by the person or persons signing the bid.
  5. The Bid shall contain no alterations or additions, except those to comply with instructions issued by the Employer (STEM), or as necessary to correct errors made by the bidder, in which case such corrections shall be initialed by the person or persons signing the bid.

 

  1. Complete Bids (including Technical and Financial) must be received by the STEM at the address/ place specified above not later than the date indicated in appendix. In the event of the specified date for the submission of bids declared a holiday, the Bids will be received upto the appointed time on the next working day. 
  2. The STEM may extend the deadline for submission of bids by issuing an amendment, in which case all rights and obligations of the STEM and the bidders previously subject to the original deadline will then be subject to the new deadline.
  3. Any Bid received by the STEM after the deadline prescribed, will be returned unopened to the bidder.
  4. Bidders may modify or withdraw their bids by giving notice in writing before the deadline.
  5. Each Bidder's modification or withdrawal notice shall be prepared, sealed, marked, and delivered in the outer and inner envelopes additionally marked "MODIFICATION" or "WITHDRAWAL", as appropriate.
  6. No bid may be modified after the deadline for submission of Bids.
  7. Withdrawal or modification of a Bid between the deadline for submission 0f bids and the expiration of the original period of bid validity specified or as extended may result in the forfeiture of the Bid security.
  8. After submission of tender (After Bid Lock) at the time of opening Tech. Bid/After opening of Tech. Bid No request of Not to open  Envelop No.2 is admissible ( Refer GOM PWD Cicrular No.CAT/2017/PK-8/EM-2 Dt.29.01.20219 Para NO.7)
  1. BID OPENING AND EVALUATION
  1. The STEMwill open all the Bids received (except those received late), including modifications made, in the presence of the Bidders or their representatives who choose to attend at time, date and the place specified. In the event of the specified date of Bid opening being declared a holiday for the Employer (STEM), the Bids will be opened at the appointed time and location on the next working day. 
  2. The envelope containing "Technical Bid" shall be opened. The amount, form and validity of the bid security furnished with each bid will be announced. If the bid security furnished does not conform to the amount and validity period as specified in the Invitation for Bid, and has not been furnished in the form specified, the remaining technical bid and the sealed financial bid will be returned to the bidder. 

 

  1. (i) Subject to confirmation of the bid security by the issuing Bank, the bids accompanied with valid bid security will be taken up for evaluation with respect to the Qualification Information and other information furnished in envelop no. 1. 

(ii) After receipt of confirmation of the bid security, the bidder will be asked in writing (usually within 10 days of opening of the Technical Bid) to clarify or modify his technical bid, if necessary, with respect to any rectifiable defects. 

(iii) Immediately (usually within 3 or 4 days), on receipt of these clarifications the Evaluation Committee will finalize the list of responsive bidders whose financial bids are eligible for consideration.

(iv) At the time of opening of "Financial Bid", the names of the bidders were found responsive in accordance with will be announced. The bids of only these bidders will be opened. The remaining bids will be returned to the bidders unopened. The responsive Bidders' names, the Bid prices, the total amount of each bid, any discounts, Bid Modifications and withdrawals, and such other details as the STEM may consider appropriate, will be announced by the STEM at the opening.

(v) The STEM shall prepare minutes of the Bid opening, including the information disclosed to those present.

(vi) Information relating to the examination, clarification, evaluation, and comparison of Bids and recommendations for the award of a contract shall not be disclosed to Bidders or any other persons not officially concerned with such process until the award to the successful Bidder has been announced. Any effort by a Bidder to influence the Employer's (STEM) processing of Bids or award decisions may result in the rejection of his Bid.

  1. To assist in the examination, evaluation, and comparison of Bids, the STEM may, at his discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit rates. The request for clarification and the response shall be in writing or by cable, but no change in the price or substance of the Bid shall be sought, offered, or permitted except as required to confirm the correction of arithmetic errors discovered by the STEM in the evaluation of the Bids.
  2. No Bidder shall contact the STEM on any matter relating to his bid from the time of the bid opening to the time the contract is awarded. If the Bidder wishes to bring additional information to the notice of the Employer (STEM), it should do so in writing.
  3. Any effort by the Bidder to influence the STEM in the Employer's (STEM’s) bid evaluation, bid comparison or contract award decisions may result in the rejection of the Bidders' bid.
  4. During the detailed evaluation of "Technical Bids", the STEM will determine whether each Bid (a) meets the eligibility criteria defined, (b) has been properly signed; (c) is accompanied by the required securities and; (d) is substantially responsive to the requirements of the Bidding documents. During the detailed evaluation of the "Financial Bid", the responsiveness of the bids will be further determined with respect to the remaining bid conditions, i.e., priced bill of quantities, technical specifications, and drawings.
  5. A substantially responsive "Financial Bid" is one which conforms to all the terms, conditions, and specifications of the Bidding documents, without material deviation or reservation. A material deviation or reservation is one (a) which affects in any substantial way the scope, quality, or performance of the Works; (b) which limits in any substantial way, inconsistent with the Bidding documents, the Employer's (STEM’s) rights or the Bidder's obligations under the Contract; or (c) whose rectification would affect unfairly the competitive position of other Bidders presenting substantially responsive Bids.
  6. If a "Financial Bid" is not substantially responsive, it will be rejected by the Employer (STEM), and may not subsequently be made responsive by correction or withdrawal of the non-conforming deviation or reservation.
  7. "Financial Bids" determined to be substantially responsive will be checked by the STEM for any arithmetic errors. Errors will be corrected by the STEM as follows: (a) where there is a discrepancy between the rates in figures and in words, the rate in words will govern; and (b) where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by the quantity, the unit rate as quoted will govern. 
  8. The amount stated in the "Financial Bid" will be corrected by the STEM in accordance with the above procedure and the bid amount adjusted with the concurrence of the Bidder in the following manner: (a) If the Bid price increases as a result of these corrections, the amount as stated in the bid will be the 'bid price' and the increase will be treated as rebate; (b) If the bid price decreases as a result of the corrections, the decreased amount will be treated as the 'bid price' Such adjusted bid price shall be considered as binding upon the Bidder. If the Bidder does not accept the corrected amount the Bid will be rejected, and the Bid security may be forfeited. 
  9. The STEM will evaluate and compare only the Bids determined to be substantially responsive.
  10. In evaluating the Bids, the STEM will determine for each Bid the evaluated Bid Price by adjusting the Bid Price as follows:
  1. Making any correction for errors or
  2. Making an appropriate adjustments for any other acceptable variations, deviations; and
  3. Making appropriate adjustments to reflect discounts or other price modifications offered.
  1. The STEM reserves the right to accept or reject any variation or deviation.Variations and deviations and other factors, which are in excess of the requirements of the Bidding documents.
  2. If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer's estimate of the cost of work to be performed under the contract, the STEM may require the Bidder to produce detailed price analyses for any or all items of the Bill of Quantities, to demonstrate the internal consistency of those prices with the construction methods and schedule proposed. After evaluation of the price analyses, the STEM may require that the amount of the performance security set forth be increased at the expense of the successful Bidder to a level sufficient to protect the STEM against financial loss in the event of default of the successful Bidder under the Contract.
  1. AWARD OF CONTRACT
  1. Not with standing, the STEM reserves the right to accept or reject any Bid, and to cancel the Bidding process and reject all Bids, at any time prior to the award of Contract, without thereby incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders of the grounds for the Employer's (STEM’s) action.
  2. The Bidder whose Bid has been accepted will be notified of the award by the STEM prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by registered letter. This letter will state the sum that the STEM will pay the Contractor in consideration of the execution, completion, and maintenance of the Works by the Contractor as prescribed by the Contract.
  3. The notification of award will constitute the formation of the Contract, subject only to the furnishing of a performance security. 
  4. The Agreement will incorporate all agreements between the STEM and the successful Bidder. It will be signed by the STEM and sent to the successful Bidder, the successful Bidder will sign the Agreement and deliver it to the Employer (STEM). 

            Upon the furnishing by the successful Bidder of the Performance Security, the STEM   

            will promptly notify the other Bidders that their Bids have been unsuccessful.

Managing Director

STEM Water Dist. & Infra. Co. Pvt. Ltd.,

Thane.

STEM WATER DISTRIBUTION & INFRASTRUCTURE CO.  PVT.LTD.,THANE

 

              Name of Work: -

 

MATERIAL SCHEDULE – A


 

Statement showing materials to be supplied to the contractor and approximate quantities and rates that are to be charged for the contractor and place of delivery.

 

Sr. No.

Particulars

Qty.

Unit

Rate at which material will be supplied

Place of Delivery

 







 

-------------- NIL -------------









 
       




 

Contractor     Managing Director

STEM Water Distri. & Infra. Co. Pvt. Ltd.

                           Thane.

STEM WATER DISTRIBUTION & INFRASTRUCTURE CO.PVT.LTD., THANE.


 

Name of Work: -

DETAILED ITEMWISE SPECIFICATIONS

Take Details Wise Specification form here

 




 

 

Managing Director,     

STEM  Water Dist. & Infra. Co. Pvt. Ltd, 

Thane






 

STEM WATER DISTRIBUTION & INFRASTRUCTURE CO. PVT. LTD., THANE

 

              Name of Work: -











 

Schedule -B




 

Attached Separately



















 

FORM OF LETTER OF APPLICATION

(Letter head of the Agency)

 

Technical Proposal

To, Managing Director,

STEM Water Dist. & Infra Co. Pvt. Ltd.

Vardan Commercial Complex, 9th Floor,

MIDC, Road No.16, Wagle Estate, 

Thane (W) – 4000 604.



 

Sub:-

Sir, 

Having examined the Bid Document, Instruction to Bidders, Conditions of contract, Scope of work with detailed specifications etc. for the subject work. We hereby submit our bid for the subject work.

It is certified that the information furnished in this document is true and correct. The proposal is unconditional and unqualified. I/We , the undersigned  unconditionally accept that STEM Water Dist. & Infra Co. Pvt. Ltd., Thane, reserves the right to reject any or all application without assigning any reason.

Thanking You,

 

Yours Faithfully,



 

(Authorized Signatory) for and on

behalf of M/s. ________________




 

 

AFFIDAVIT

(Letter head of the Agency)

Name of work:-

 

  1. I, the undersigned, do hereby certify that all the statements (document & certificate attached) made in the required attachments are true and correct. 
  2. The undersigned also hereby certifies that neither our firm M/s._________________________________________________________ have abandoned any work/ nor any contract awarded to us for such works have been rescinded, during last five year prior to the date of the bid.  (In STEM or in Government/ Semi Government organisations).
  3. The undersigned hereby authorize (s) and request(s) any bank, person, firm or corporation to furnish pertinent information deemed necessary and requested by the Department to verify this statement or regarding my (our) competence and general reputation. 
  4. The undersigned also furnish undertaking that we are not declared by any court of law as proclaimed offenders also that we are not convicted under any law for the offences punishable under Indian Penal Code, TADA, POTA, Negotiable Instrument Act, or any Labour / Employee beneficial legislation’s.
  5. Our firm M/S. ___________________________________________________ have not Black listed / Cancellation of Registration Proposed for Black listing / Cancellation of Registration in any Govt. /Semi Govt. Dept. / Municipal Corporations / PUC’s (including Partner / Joint Venture Partner if any) or in process of Blacklisting, Cancellation of Registration.
  6. If our offer is below to the estimated cost put to tender we hereby undertake that required Additional Performance Security Deposit in form of D.D./F.D.R.B.G of Nationalized Bank will be submitted within 8 days from the date of intimation letter from STEM. We further undertake that f we fail to submit Additional Performance Security Deposit in those 8 days period then our offer shall stand rejected. No extension for said period will be allowed to us.
  7. The undersigned understand and agrees that further qualifying information may be requested, and agrees to furnish any such information at the request of the Department, Project implementing agency / STEM within stipulated period.

 

_____________________________________________

 (Signed by Authorized Officer of the Firm)


 

________________________

Title of Officer


 

_________________

Name of Firm

 

________________

DATE

 

(Note: - This Affidavit is to be submitted/uploaded in Envelope No. 1 by the Bidder)

(Refer GOM, PWD GR No.CAT/2018/PK.127/EM-2 Dt.28.11.2018)

UNDERTAKING

(On letter head of agency)

 

Name of work:-


 

  1. I, the undersigned do hereby undertake that our firm M/s ----------------------------------wouldinvest a minimum cash up to 25% of the work during implementation of the Contract.
  2. The undersigned do hereby undertake that our firm M/s._____________________agree to abide by this bid for a period 60 days for thedate fixed for receiving the same and it shall be binding on us and may be accepted at any timebefore the expiration of that period and also for the period if validity is duly extended.

 

 


 

_____________________________________________

 (Signed by Authorized Officer of the Firm)



 

________________________

Title of Officer



 

_________________

Name of Firm



 

________________

DATE





 

 

Affidavit (on Rs.100/- Stamp Paper)

 

Name of work:-


 

I .................................................... age ......................................address ....................................... (Authorized signatory to sign the contract), hereby submit, vide thisaffidavit in truth, that I am the owner of the contracting firm .................................... / authorized signatory and I am submitting the documents in envelope no.1 for the purpose of scrutiny of the contract. I hereby agree to the conditions mentioned below :- 

 

  1. I am liable for action under Indian Penal Code for submission of any false / fraudulent paper / information submitted in envelope no.1.

 

  1. I am liable for action under Indian Penal Code if during contract period and defect liability period, any false information, false bill of purchases supporting proof of purchase, proof of testing submitted by my staff, subletting company or by myself, I will be liable for action under Indian Penal Code.

 

  1. I am liable for action under Indian Penal Code if any paper are found false / fraudulent during contract period and even after the completion of contract ( finalisation of final bill).




 

(Signature of contractor)

(seal of company)


 

(Note: - This Affidavit is to be submitted/uploaded in Envelope No. 1 by the Bidder)

(Refer GOM , PWD GR No. CAT/2018/PK.127/EM-2 Dt.28.11.2018)



 

FORM OF BID

(For Percentage Rate )  B1

(To be attached in Envelop No. 2)

 

To, 

Managing Director,

STEM Water Dist. & Infra Co. Pvt. Ltd.

Vardan Commercial Complex, 9th Floor, 

MIDC, Road No. 16, Wagale Industrial Estate,

Thane (W)-400 604.

 

Description of the Works:-.....................................................................................................................

...................................................................................................................

1. We offer to execute the Works described above and remedy any defects therein in conformity with the conditions of Contract, specification, drawings, Bill of Quantities and Addenda for the sum(s) of  Rs. ____________________ (Rs. ______________________________________________Only) inclusive all taxes, duties etc. i.e. _______% Above/ Below the estimated cost Rs. _______________.

 

2. We undertake, if our Bid is accepted, to commence the Works as soon as is reason-ably possible after the receipt of the notice to commence, and to complete the whole of the Works comprised in the Contract within the time stated in the document. 

 

3. We agree to abide by this Bid for the period of 60 days from the date fixed for receiving the same, and it shall remain binding upon us and may be accepted at any time before the expiration of that period/ extended validity period.


 

4. Unless and until a formal Agreement is prepared and executed this Bid, together with your written acceptance thereof, shall constitute a binding contract between us. 

 

5. We understand that you are not bound to accept the lowest or any tender you may receive.

Dated this .......................day of ......................... 20.................

Signature _______________________ in the capacity of _________duly authorized sign

bids for and on behalf of ......................................................................................................

(in block capitals or typed)

Address

................................................................................................................................................

Witness

................................................................................................................................................

Address

................................................................................................................................................

Occupation

................................................................................................................................................

Note-The bidder shall submit/ upload this form dully filled with his financial offer (in envelop No. II). 





 

PERFORMANCE BANK GUARANTEE

(Letterhead paper of the STEM)

 

To,

Managing Director,

STEM Water Distri. & Infra. Co. Pvt. Ltd.,

9th floor, Vardan Commercial Complex, 

MIDC, Road No. 16, Wagale Estate, 

Thane (W)

 

WHEREAS ________________________________ [name and address of Contractor] (hereafter called “The Contractor”) has undertaken, in pursuance of Contract No. ___________ dated __________ to execute _________________ [name of Contract and brief description of Works] (hereinafter called “the Contractor”)

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee.

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you on behalf of the Contractor, up to a total of ______________________ [amount of guarantee]* ________________________(in words), such sums being payable in the types and proportions of currencies in which the Contract Price is payable, and we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums within the limits of ____________________________ [amount of guarantee] as aforesaid without your needing to prove or to show ground or reasons for your demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the contractor before presenting us with the demand.

We further agree that no change or addition to or other modification of the terms of the Contract or of the Works to be performed thereunder or of any of the Contract documents which may be made between your and the Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such change, addition or modification.

This guarantee shall be valid 28 days from the date of expiry of the Defect Liability Period.

 

Signature and Seal of the Guarantor _______________

Name of Bank ________________________________

Address _____________________________________

Date __________


 

* An Amount shall be inserted by the Guarantor, representing the percentage the contract price specified in the Contract including additional security for unbalanced Bids, if any and denominated in Indian Rupees.

* Bank Guarantee shall be only of Nationalised Bank/ Scheduled Bank.



 

Letter of Acceptance

(Letterhead of the STEM)

 

To,

____________________________ (Name and address of the contractor)

____________________________

____________________________


 

Dear Sirs,

 

This is to notify you that your online bid dated ____________ for execution of the ______________________________________ (name of the contract and identification number, as given in the Instructions to Bidders) for the Contract Price of Rupees ___________________________ (______________) (amount in words and figures), as corrected modified and negotiated, is hereby Proposed for acceptance/ Under consideration for acceptance.

You are hereby requested to furnish original Performance Security, an amount equivalent to Rs. _____________ in the form of D.D./ F.D.R./ B.G. in the Name of Managing Director, STEM Water Distribution & Infrastructure Co. Pvt. Ltd. within 07 days of the receipt of the letter of acceptance valid up to 28 days from the date of expiry of defects Liability Period i.e. up to _______________and sign the contract with other requirements/ documents required as per terms of contract (i.e. initial security deposit etc.) failing which further action will be taken (including forfeiting EMD etc.).

Thanking You.

 

Yours faithfully,



 

Managing Director

STEM Water Distri. & Infra. Co. Pvt. Ltd.

Thane




 

 

AGREEMENT FORM

(Rs. 100 Stamp Paper)

Agreement

 

This agreement, made the ___________ day of _____________between __________ (Managing Director, STEM Water Distri. & Infra. Co. Pvt. Ltd., 9th floor, Vardan Commercial Complex, MIDC, Road No. 16, Wagale Estate, Thane (W)) [hereinafter called “the Employer] and ______________________ (name and address of contractor) hereinafter called “the Contractor” of the other part.

Whereas the employer is desirous that the Contractor(name and identification number of Contractor) ()(hereinafter called “the Works”) and the Employer (STEM) has accepted the Bid by the Contractor for the execution and completion of such Works and the remedying of any defects, any Manufacturing defects etc. up to DLP therein, at a cost of Rs____________ (i.e. _____% Above/ Below to the estimated Cost Rs._____________)

NOW THIS AGREEMENT WITNESSTH as follows : (1) In this Agreement, words and expression shall have the same meanings as are respectively assigned to them in the conditions of contract hereinafter referred to and they shall be deemed to form and be read and construed as part of this Agreement. (2) In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the Contractor hereby covenants with the Employer to all aspects with the provisions of the contract. (3) The Employer hereby covenants to pay the Contractor in consideration of the execution and completion of the Works and the remedying the defects wherein Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the Contract. (4) The following documents shall be deemed to form and be ready construed as part of this “Agreement”.

  1. 1. (i) Letter of Acceptance (LOI & Work Order) (ii) Notice to proceed with the works (iii) Contractor’s Bid (iv) Condition of contract : General and Special (v) Contract Date (vi) Additional/ Special condition (vii) Drawings (viii) Bill of Quantities(ix) Minutes of Prebid meeting (x) and Any other documents listed in the Contract Data as forming part of the Contract. 2. (a) The said tender and appendix there to, including Press Notice, Detailed Tender Notice, Corrigendum, Extensions. (b) Any other conditions of contract and annexure’s. (c) The specifications. (d) The bill of quantities schedule `B'. & schedule `A' (e) The schedule of particulars. (f) The addenda. (g) Form B1 & Drawing’s. (i) Security Deposit, Additional Security Deposit in form of F.D.R./B.G./D.D (j) Partnership deed, collaboration deed, joint venture, PoA.

 

  1. Security Deposit, in form of D.D./ B.G/ F.D.R. No.________________ dated__________ Rs_____________/- of                             (Bank) is hereby fully discharge for payment in favour of Managing Director, STEM Water Distribution& Infrastructure Co. Pvt. Ltd,

 

  1. In consideration of the payment to be made by the Employer to the contractor as herein after mentioned the contractor hereby covenants with the owner to execute the work in conformity with the provisions of the contract.

 

  1. All Correspondence between Employer & ContractorANDPapers from Press Tender Notice to Security Deposit & final work order of this work shall be form part and parcel of this agreement.

In witnessed whereof the parties there to have caused this Agreement to be executed the day and year first before written.

 

The Common Seal of Employer& M/s. _________________________________ was hereunto affixed in the presence of : Signed, Sealed and Delivered by the said both parties. (the Employer& the contractor)

in the presence of ; witness.

Place: Thane.

Contractor / Consultant / Service Provider

M/s.____________________________ ________________________________               

                 (Name of Signature holder)/ (POA Holder)

                 PAN No. _______________

STAMP

 

 

Managing Director,     

STEM  Water Dist. & Infra. Co. Pvt. Ltd, 

Thane

STAMP


  Witness Witness

1) Sign____________________________ 1) General Manager, STEM (Name& Sign.)

Name: __________________________

Address :________________________

PAN No.:

 

2) Sign____________________________ 2) Accounts Officer / Deputy Engineer STEM 

Name: __________________________ (Name & Sign.)

Address :________________________

PAN No.:

 

 

 

Issue of Notice to proceed with the work

(Letter head of the STEM)

__________________(Date)

To,

________________________ [name and address of the Contractor]

________________________

________________________

 

Name of Work:-____________________________________________________

____________________________________________________

 

           Ref:- 1) A/T No._________  Year______________

           2) Work Order No.__________ Date:-_________________


 

Dear Sirs,

  1. Pursuant to your furnishing the requisite security as stipulated signing of the Contract for the work of...................................................................................Bid Price of Rs.____________ .(i.e._________% Above/ Below to the estimated Cost Rs. _______________)

 

  1. Pursuant to your furnishing the requisite copies of insurances drawn for the subjected contract for the work. You are hereby instructed to proceed with the execution of the said works in accordance with the documents.

 

Yours faithfully,

(Managing Director/ General Manager/ Deputy Engineer)

For STEM Water Distri.& Infra. Co. Pvt. Ltd.